https://drive.google.com/open?id=1VG3AXKkhL-MIoBrOJazfOSwpbvxu-NfD
System and Subsystem Reviews
Technical reviews may take place at either the system or the sub-system level,
dependent on the structure of the project and the timing of specific elements of the task.
The initial reviews, covering the SCR and the SDR, should take place at system level if
they are to be effective in ensuring that the project definition properly recognises the total
set of requirements, as well as the integration and interfaces between elements of the
task. The SDR may be preceded by sub-system level reviews if this is necessary due to
the complexity of the task.
The System Concept Review (SCR) is carried out during feasibility stage after the
preparation of a detailed statement of requirement for the project, but prior to a Request
for Tender (RFT) being released. It is normally only applicable for large-scale high
complexity projects such as a new line or major reconfiguration of existing infrastructure.
The primary purpose of the SCR is to determine whether the operational, engineering
and support requirements for the asset have been fully defined and that the requirements
of the proposed RFT provide a sound and comprehensive statement of the product and
services required within a contract.
Purpose
The purpose of the System Concept Review (SCR) is to determine whether the
operational, engineering and support requirements for the proposed acquisition project
have been fully defined and that the resultant specifications and Request for Tender
(RFT) provide a sound basis for ensuring that customer requirements can be met.
The specifications and the requirements of the contract arising from an RFT form the
primary basis for all technical review activity carried out as part of the project. It follows
that the success of the review process depends directly on the effort invested in bringing
these documents to a high standard prior to letting a contract.
13.2 Scheduling the review
Review of the requirements to be included in the SCR may take place progressively as
part of the lead-up effort to preparing a final version of the RFT. However it is important
that a final, formal, SCR should take place, to provide the opportunity for multi-disciplinary
review of the final requirements and the structure of the total contract task. This review
often reveals inconsistencies in the requirement which may not be evident from
independent “small group” reviews.
Scheduling of the formal SCR should provide sufficient time for corrective action to be
taken and for changes to be made to the documentation prior to final release. There is
little purpose in conducting the review unless this outcome can be assured.
Ideally the review should be scheduled two to three weeks ahead of the planned release
date for the RFT and at the stage where the specification and technical requirements of
the Statement of Work exist in at least advanced draft form. Any shorter period imposes
major constraints on the process and planning for the preparation and release of the RFT
should include a firm milestone for conduct of the SCR.
General guidelines
The primary focus of the SCR is to ensure that the requirements specified for the
proposed acquisition are realistic, complete and cohesive.
In most cases this does not require minute examination of specification requirements but
rather assurance that the total set of requirements has been specified in a way which
meets operating and performance needs by the most efficient means.
Most importantly, the SCR provides a final opportunity to review and assess the
statement of requirement which represents the performance requirement for a binding
contract. Decisions taken at this point have the potential to lead to a contract which
provides a sound basis for contractor performance and customer satisfaction, or one
which leads to an inferior product and/or to a large number of variations and the attendant
increase in total project cost.
14.1 Purpose
The purpose of the System Definition Review (SDR) is to verify that the requirements of
the contract task have been assessed and understood by the contractor, subsequent to
contract award. The review is carried out to ensure that possible uncertainties and
misunderstandings are resolved as early as possible in the contract and before work
commences on the detail design process.
Celem przeglądu definicji systemu (SDR) jest sprawdzenie, czy wymagania zadania kontraktowego zostały ocenione i zrozumiane przez wykonawcę po udzieleniu zamówienia. Przegląd przeprowadza się w celu zapewnienia możliwych niepewności i
nieporozumienia są rozwiązywane jak najwcześniej w umowie i przed rozpoczęciem prac nad procesem projektowania szczegółowego.
14.2 Scheduling
The SDR should be scheduled as soon as practicable after the contract has started, but after a sufficient time to permit the contractor to have completed a preliminary design synthesis. This period varies between projects and the actual time should be set by
agreement with the contractor.
14.2 Planowanie
SDR powinien być zaplanowany tak szybko, jak to możliwe po rozpoczęciu umowy, ale po upływie wystarczającego czasu, aby umożliwić wykonawcy wykonanie wstępnej syntezy projektu. Okres ten różni się w zależności od projektu, a rzeczywisty czas powinien zostać ustalony w porozumieniu z wykonawcą.
14.3 Responsibilities
The Project Manager is responsible for arranging the SDR and for establishing the agenda for the meeting. The SDR meeting should be chaired by the Project Manager. Agenda items raised by the contractor should be advised to participants in advance of the meeting, to allow time for review and internal resolution of any requirements.
14.4 Participants
Participants in the SDR are nominated by the Project Manager or Principal Engineer as appropriate and should be selected on the basis of their responsibility for some aspect of the project task.
Potencjalni czytelnicy (Uczestnicy)
Uczestnicy SDR są odpowiednio wyznaczani przez kierownika projektu lub głównego inżyniera i powinni być wybierani na podstawie ich odpowiedzialności za niektóre aspekty zadania projektowego.
14.5 Prerequisites
The prerequisite for the review is the delivery of design and documentation as required by
the contract (refer EPD 0013 Appendix A).
14.6 Exit criteria and objectives
Exit criteria should be established by the Project Manager in advance of the SDR, to
reflect specific circumstances of the contract.
14.7 Specific outcomes
Specific outcomes of the SDR are a direct function of the issues raised at the review.
Under normal circumstances the review identifies a number of aspects requiring
clarification which should be accepted as action items, either by the Project Manager or
the contractor.
A specific target date should be agreed for completion of each action item, to ensure that
the project is not delayed and to avoid any potential for later claims for excusable delay,
due to lack of clarity in the requirement.
The SDR should establish the preliminary Functional Baseline for the project, for
confirmation at the PDR.
General guidelines
The SDR process is intended primarily as an opportunity to review, discuss and resolve
any aspect which may lead to unnecessary conflict and delays in the development
process later in the project.
Proces SDR ma przede wszystkim być okazją do przeglądu, omówienia i rozwiązania wszelkich aspektów, które mogą prowadzić do niepotrzebnego konfliktu i opóźnień w procesie rozwoju w późniejszym okresie projektu.
Wymagania operacyjne
Functional Requirement
Wymagania funkcjonalne
Operating Concept
Koncepcja operacyjna
Maintenance and Support Concept
Koncepcja konserwacji i wsparcia
Service Life
Environmental Specification
Specyfikacja środowiskowa
Operational Interfaces
Interfejsy operacyjne
Wymagania programowe
Program Schedule
Harmonogram programu
Designed Reviews
Specific Reviews Nominated
Defined Scope
Responsibilities
Contract Milestones
Kamienie milowe umowy
Quality Assurance
Zapewnienie jakości
Specified Standard
Test Articles
Alignment with
Configuration Management
Zarządzanie konfiguracją
• Review initial proposals for designation of configuration items.
• Review initial proposals for specification hierarchy, if appropriate for the program.
• Agree basis for establishing the Functional Baseline.
NOTE: The above aspects are closely associated with discussion of the status of the functional specification and also preliminary design synthesis. These are covered under systems engineering and may be combined in a single topic.
• Przejrzyj wstępne propozycje wyznaczenia elementów konfiguracji.
• Przejrzyj wstępne propozycje hierarchii specyfikacji, jeśli jest to właściwe dla programu.
• Zgadzam się z podstawą do ustalenia funkcjonalnej linii bazowej.
UWAGA: Powyższe aspekty są ściśle związane z omówieniem statusu specyfikacji funkcjonalnej, a także wstępnej syntezy projektu. Są one objęte inżynierią systemów i mogą być połączone w jednym temacie.
Documentation
Dokumentacja
Specified Requirement (General)
Określone wymagania (ogólne)
Inżynieria systemowa
Design Specification
Specyfikacja projektowania
Design Standards
Standardy projektowania
Requirements Traceability
Design Synthesis
Status of Development Task
Synteza konstrukcyjne
Status zadania rozwojowego
Standardisation
standaryzacja
Interface Definition and Management ?
Review contractors understanding and assessment of defined interface specifications and documents.
• Review proposed means of interface control, particularly where major subcontractors are involved in the project.
Definicja interfejsu i zarządzanie
Przejrzyj zrozumienie kontrahentów i ocenę określonych specyfikacji interfejsów i dokumentów.
• Przegląd proponowanych środków kontroli interfejsu, w szczególności w przypadku, gdy w projekt zaangażowani są główni podwykonawcy.
Drawings and Documentation
Standards Delivered Documents ?
Rysunki i dokumentacja
Software
Oprogramowanie
Koncepcja Zintegrowanego Wsparcia
Maintenance / Inspection Requirements
Wymagania Konserwacja / inspekcyjne
Spares Support
Części zamienne Wsparcie
Training
Szkolenie
Support Equipment
Sprzęt pomocniczy
Facilities
Udogodnienia
Operating and Support Documentation
Dokumentacja obsługi i wsparcia
Packaging
Opakowanie
Planning Verification and Test
Planowanie weryfikacji i testów
Integration
Integracja
Qualification
Kwalifikacja
First article inspection
https://en.wikipedia.org/wiki/First_article_inspection
Commissioning
Uruchomienie