Service Manager - Projects
Overview
Projects are used to manage at a high level - days rather than hours.
Projects support three indented levels as follows
Level 1 (grey) - Project Phase or Major Deliverable
Level 2 (blue) - Key Activities or Work Packages
Level 3 (green) - Specific Tasks or Actions
Projects can be used to generate
Quotations - Transaction Items are created from the Root level Items on the Project
Progress Invoices - Transaction items are created from Components based on their Completion % and the difference between the Completion percent on the last invoice.
Actions
Add Project Templates
Batch Update
Update Start and End Dates
Set start-to-finish Dependency (SF)
Clear Dependency
Delete - delete multi-selected items
Fields
Level - The indentation (level) is represented by the grey, blue and green icons.
Status - The Status list is derived from the Template. Multiple Templates can be added to a Project, each with their own Status list.
Description
Groups - Groups are mostly used for filtering and reporting. Right-click to Add/Remove Groups to the selected item.
Constraint - Select aa valid option from the dropdown list
Resource - Select from the dropdown list.
Billing - Select from None, Fixed, Variable. Applies to first level only.
Required - The Required date,
Start - The Start date
End - The End date
Days - The expected duration - decimals and negative values are not supported.
Hours - The hours estimated to complete the Task - used for costing purposes.
Note - Right-click an item to View/Edit Note
Project Resources
List of your company's Resources including Departments, Work Centres and Staff.
The Hourly Rate is used for Costing purposes, for instance, when you generate a Quotation from the Project.
Resources can be applied to
Level 1 - for Quoting/Costing purposes - ideally a generic Resource will be applied - eg. Consultant.
Level 3 - for assigning Tasks.
Components
An ordered list of Components can be integrated into the Project Plan.
Components can be added directly in the Project or imported from the Items of a transaction linked to the Project and linked to the Transaction Setting > Transaction used for Quotations.
Components can be used to generate Progress Invoices using the Total and Completion %.
Component Example (Joinery):
Groups: Floor 1, Floor 2
Components: Wardrobe, Bar Cabinets, Kitchen Units
Project Templates
The Project Templates are linked to a Class and consist of Items and a Status list that can be appended to a Project.
The Items are a mini project that starts at Level 1 and can optionally contain Level 2 and Level 3 items. Multiple Level 1 items can be added to create a template that is effectively a complete project plan.
The Components field is used to enable a Component Placeholder and set the Level at which components will be merged. Options include:
Don't Use - the template will not be merged with Components.
Level 1 - The Component will replace the Level 1 item.
Level 2 - The Component will replace the Level 2 item.
Notes
When a template is added to a Project, the Items and Status list is copied to the SM so that changes to the template won't affect historic Projects.
Only one Component Placeholder is allowed in a Template.
Rules for updating the Project Start and End dates
Calculation is applied to Level 3 and rolled up to Level 2 and Level 3.
Update starts at bottom or top depending on Tracker constraint - ASAP - Top (Start Date on Tracker) - Alap - Bottom (Required)
Weekend Days and Holidays are considered when updating Days and End dates. For instance, if a Task takes two days and starts on a Friday, the End date will be set to Monday.
Item Updates
Start - Updates End
End - Updates Start
Days - Updates End
Constraints
Level 1
Fixed - The Start, End and Days is fixed in all the descending items.
ASAP - As Soon As Possible
ALAP - As Late As Possible
Level 2, 3
None
Fixed - Start, End and Days are fixed.
NB. If an Item is Fixed with blank Start and End dates, the cascading Items will not be scheduled.
Dependencies
Dependencies can be applied at the same level in the same group only
Dependencies are cleared when the Dependency is below the item (after moving item or dependent item) or the Constraint is set to Fixed.
Settings
Transaction Settings > Service Manager
Transaction used for Progress Invoices - (Can add multiple settings)
Transaction used for Quotations (Can add multiple settings) - Used to import Components and to generate Quotations from the Project.