Eva Report
03/26/2013
Corentin Liber
Eva Number:
1
Eva Date:
03/26/2013
Time Slot:
laterAM
Purpose:
Two crew members went on EVA to the survey area for the stream bed project.
The needed data was collected in the main bed as planned.
Narrative:
Two of the crew members left the airlock after decompression time for a data collecting mission.
They went to the survey area and measured the needed data in 13 points along the stream bed.
The data was: wetted perimeter, depth and inclination of the slope.
We also checked at regular times if the communication with the base was good enough. At some points, it was impossible to contact because of the interference due to the relief. A future EVA will test the communication in the whole area around the test site to be sure to avoid connection problems in case of an emergency.
Eva Depart Time:
9:40
Eva Return Time:
11:35
Wp1 E:
518870E
Wp1 N:
4251800N
Waypoint1arrive Time:
10:00
Eva W P1depart Time:
11:10
______________________
CommanderCheckIn Report
03/26/2013
Nicolas Roelandt
Crew Physical Health:
One of us had a little diarrhea but it wasn't severe.
Eva Depart Time:
9h30
Eva Return Time:
11h30
Narrative Of Field Mission Results:
Collecting data for the river
Eva Depart Time:
16h20
Eva Return Time:
17h40
Narrative Of Field Mission Results:
Finish Xbee Calibration
Eva Depart Time:
Eva Return Time:
Narrative Of Field Mission Results:
Eva Depart Time:
Eva Return Time:
Narrative Of Field Mission Results:
Eva Depart Time:
Eva Return Time:
Narrative Of Field Mission Results:
Hab Maint:
Adrien (Crew Engineer) fixed the two broken chairs.
Rep Sched:
/
Tomorrow Plan:
Test average speed for long distance walk.
Collect data of the river affluents.