New rules that have become applicable starting with version 13.03
1. MatchPO and MatchINV - both are included in the costs depending on the value in the Receipt Match Requirement field in the Material Receipt window;
2. The Receipt Match Requirement field in the Material Receipt window is mandatory and it appears from the Drafted version filled in with the default value set at Tenant level; after posting the receipt, the field will become non-editable;
3. Always the existence of the costs when posting the MatchINV and MatchPO;
4. In order to change the "Match Requirement" value you need to de-post the material receipt, including the MatchINV or MatchPO, that has influenced the costs.
New rules for the WAC method that have become applicable starting with version 13.07
1. Voiding exit documents (positive quantitative entry) modifies the cost WAC value.