Project editing screen

The tree list provides general information about project:

  • the project name,
  • the edition number and date,
  • the project begin date,
  • the project end date, or the essential and total end dates if they are not the same,
  • the estimated duration in weeks, and a warning message if project duration overpass estimated duration,
  • responsible name and project content, when they have been filled,
  • project calendar information classified by categories (not worked weekdays, not worked annual days...),
  • the inputs, outputs and comments when they have been filled.

When a line is selected (name, begin time, estimated duration, content, calendar information), action bar commands allow to change data, and to delete line if it is authorized (content, calendar information).

When there is no selected line, the options menu allows then:

  • to add an unfilled information field (responsible, content, inputs, outputs, comments), the text update box is displayed and text must not be leaved blank to be taken in account,
  • to add calendar information (not worked day or range, exceptionally worked date),
  • to reset calendar from one of existing defaults (FR, GB, US, other) or from preferences calendar,
  • to reset to 1 the edition number after confirming (it is recommended then to modify also the project name to avoid problems when saving).