Once the insulation has been installed, the Project Manager will need to create a To-Do to ask the Trade Partner (usually James Hinkle) to send a PDF file of the insulation (ICC) report. If paint had to be used, they would also need a copy of the report for the paint. Once the report has been sent, the PM will need to tag Vienna Mortel and ask them to attach the PDF file to the Remodeling Permit for the Inspector to view. This will help the Inspector to have all the information needed to approve the Insulation Inspection. This step HAS to be complete before drywall work can begin.