The purpose of this procedure is to establish the minimum requirements for setting up the Auto Loading Page on Electric Drive units in the LOGIX control panel. The procedure applies to all Electric Drive LOGIX panels equipped with the Auto Loading feature option. This procedure is to ensure the proper set up of the Electric Drive Auto Loading Page to ensure full PLC control of RPM and loading in the LOGIX panel as laid out in this procedure.
This procedure applies to all Electric Drive units that are equipped with the LOGIX panel that has the Auto Loading Page Control Mode option currently in service in the Field, Test Loop, at a Repair Shop, or in Storage Yards. Flogistix Service Technicians will perform the set up of the Auto Loading Page in the LOGIX panel as laid out in this procedure according to this procedure.
Before any work is performed a JSA needs to be done according to Flogistix procedure along with any Customer requirements before any work is started.
Management - Management is responsible for implementing, supporting, and enforcing the requirements of this procedure to their respective locations/area.
EHSS - Responsible to assist in the implementation of this procedure and to review for effectiveness.
Employees, Contractors, Vendors, ETC. - Are responsible to follow the requirements outlined in this procedure and ask for assistance
This procedure applies to all Flogistix Electric Drive compressor units equipped with a LOGIX control panel with the Auto Loading feature option and are applicable to all Flogistix employees, contractors, and temporary employees.
Employees should be aware that units could contain flammable and toxic gasses. Potential for the possible hazards of gas ignition or fire, hot surfaces & fluids, rotating equipment. Risk of possible concentration of H2S. Hazardous gases could be in the units pressure vessels, cooler, or associated piping and risk of inhalation of hazardous gas fumes.
All Personal Protective Equipment (PPE) for normal Field Mechanical duties apply for this procedure.
Four Gas Monitor, which is outlined in the Flogistix EHSS Manual, PPE Section 8, Procedure 8.3
This procedure applies to all units in service in the field, at a service shop, or in any storage yard.
Insure Flogistix personnel have proper safety certification or site orientation if required by the Flogistix Customer.
Insure Flogistix personnel adhere to all Customers safety practices.
All employees shall be initially trained on the following topics:
Employee Personal Protective Equipment (PPE)
Lock Out Tag Out (LOTO) procedure according to Flogistix policy
Emergency and First Aid procedures
Methods and Observations that may be used to detect the presence or release of a hazardous chemicals or gas in the work place
Basic LOGIX panel training
Tools & Equipment Required
All employees performing this procedure shall be required to have the listed tools to perform job tasks:
All required PPE according to Flogistix Safety Policy
Approvals
Field Service approved by:
Date:
Engineering approved by:
Date:
EHSS approved by: