HIGH PRIORITY - Safety, Compliance, Instruction, Activities
We have received a donation for some gravel to go down around our the parking area of our baseball diamond. Could we use the dump bed trailer sometime in the next two weeks to haul the gravel? If John is available help us haul it that would be great. If he is not available we can use the truck from MES to pull it so we don't tie him up. I will have the company sign the new district donation form when we pick up the gravel.
Location: 708 - Milford High School
Reported By: Principal
Date of Request: 2.26.14
Target Completion Date: Next 2 Weeks
Date Materials Were Ordered:
Status:
38 small accent lights are out.
Location: 104 - Belknap Elementary School
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Sprinkler heads are too high (east side along the sidewalk. The snow plow keeps breaking them).
Location: 104 - Belknap Elementary School
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Leaky drain in east sink along north wall
Location: 112 - Minersville School
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Camera Repairs
Location: District-Wide
Reported By: Superintendent & Business Administrator
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Annual Self-Inspection Surveys
Location: District-Wide
Reported By: Business Administrator
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Annual Outdoor Water & Sprinkler System Prep, Inspections, Repairs
Location: District-Wide
Reported By: Business Administrator
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Custodial Supplies Orders
Location: District-Wide
Reported By: Business Administrator
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Security Door System Repairs
Location: District-Wide
Reported By: Business Administrator
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
MEDIUM PRIORITY
Change out light switch from the key type to the toggle type.
Location: 104 - Belknap Elementary School
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Kindergarten parking lot security light is out.
Location: 104 - Belknap Elementary School
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Kitchen: Middle drain has a slow leak
Location: 108 - Milford Elementary School
Work with school custodian on the following (including ordering materials)
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Kitchen: Middle handle leaks
Location: 108 - Milford Elementary School
Work with school custodian on the following (including ordering materials)
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Kitchen: PVC pipe under triple sink drips
Location: 108 - Milford Elementary School
Work with school custodian on the following (including ordering materials)
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Several ceiling tile are stained and/or broken (custodian can do this)
Location: 108 - Milford Elementary School
Work with school custodian on the following (including ordering materials)
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Outdoor light over one of the classroom exits on east side needs to be replaced.
Location: 108 - Milford Elementary School
Work with school custodian on the following (including ordering materials
Reported By: Superintendent & Principal)
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
P.A. system on stage needs to be adjusted.
Location: 108 - Milford Elementary School
Work with school custodian on the following (including ordering materials)
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Siding is loose on west side of building (one piece only)
Location: 108 - Milford Elementary School
Work with school custodian on the following (including ordering materials)
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Current water spot on ceiling tile; Office hallway (custodian) (need to check for leak in ceiling)
Location: 112 - Minersville School
Work with school custodian on the following (including ordering materials)
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Door from media to office: turn hardware around so there will have no access from media
Location: 112 - Minersville School
Work with school custodian on the following (including ordering materials)
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
They need a splashguard behind sink in kitchen.
Location: 112 - Minersville School
Work with school custodian on the following (including ordering materials)
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Light is showing through the bottom of almost all outside doors. The bottom weather stripping needs to be replaced.
Location: 112 - Minersville School
Work with school custodian on the following (including ordering materials)
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Ceiling tile in 7th/8th grade halls need to be replaced (custodians)
Location: 112 - Minersville School
Work with school custodian on the following (including ordering materials)
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
Ceiling tile in FHA room (custodians)
Location: 112 - Minersville School
Work with school custodian on the following (including ordering materials)
Reported By: Superintendent & Principal
Date of Request: 2.26.14
Target Completion Date:
Date Materials Were Ordered:
Status:
LOW PRIORITY