SID PROJECT COMPLETION AND ASSESSMENTS---

Post date: Jun 03, 2009 8:34:3 PM

It is anticipated and planned that the Project Engineers will certify the completion of the Waste Water Collection and Treatment Project for the Johnson Lake SID#1 at the Board of Trustee's July 1st Meeting (@3:00 p.m.). At this time, the Board will establish the dates for Publication of the Calculated Assessments against each benefited property within the District's boundary as well as a Public Meeting and Hearing Date for anyone objecting thereto. These are anticipated for the later part of July; with the actual levy of the assessments sometime before mid-August. Payment must be made within 50 days of this levy date of either the full amount or 1/15 of the principal; with the balance to be paid over the next 15 years bearing annual interest on the unpaid amount. More details will be forthcoming.