Project Schedule
OVERALL CONSTRUCTION TIME OF 23 DAYS
September 2, 2019 to October 10, 2019
Planners with Manners strives to bring our clients satisfaction through producing quality work in a timely manner. To do so, we work with efficiency and attention to detail. Our schedule shows our weekly progress and work breakdown structure for 2 excavators and 4 trucks.
Work Hours
Work Hours
7:00am to 4:00pmNo work on Saturday and Sunday
Public Holidays
Public Holidays
September 13 - Mid Autumn FestivalOctober 1 to 7 - National Day
Phase 1
Duration: 5 days
Volume: 4283.7 lm3 of soil moved
Haul Distance: 139km
Phase 2
Duration: 7 days
Volume: 5750.6 lm3 of soil moved
Haul Distance: 79km
Phase 3
Duration: 2 days
Volume: 2296.1 lm3 of soil moved
Haul Distance: 41km
Phase 4
Duration: 3 days
Volume: 2501.9 lm3 of soil moved
Haul Distance: 39km
PROJECT MANAGERS
PROJECT MANAGERS
Pauline Fuentebella 1424833Maksym Kadziela 1469175David Laschuk 1461513Jennifer Si 1436244
CONTACT US
+1 (306) 123 - 4567409 Construction DriveEdmonton, AB T6V A1BCONTACT US