September 2, 2019 to October 10, 2019
Planners with Manners strives to bring our clients satisfaction through producing quality work in a timely manner. To do so, we work with efficiency and attention to detail. Our schedule shows our weekly progress and work breakdown structure for 2 excavators and 4 trucks.
Phase 1
Duration: 5 days
Volume: 4283.7 lm3 of soil moved
Haul Distance: 139km
Phase 2
Duration: 7 days
Volume: 5750.6 lm3 of soil moved
Haul Distance: 79km
Phase 3
Duration: 2 days
Volume: 2296.1 lm3 of soil moved
Haul Distance: 41km
Phase 4
Duration: 3 days
Volume: 2501.9 lm3 of soil moved
Haul Distance: 39km