Earth Hauling Production
The equipment productivity that govern each earth hauling path above was calculated by determining whether using a dozer or a dump truck would provide a better productivity for hauling earth material. This equipment productivity was then compared with the productivity of the excavator to determine which equipment would govern the job.
Crew of Each Job
The unit cost for each job is shown above for each crew type.
Sequencing of Jobs
The sequencing of each job is listed above including the haul volume in bank cubic meters and loose cubic meters. The crew productivity and the duration of each job is also given.
Cost Estimation
Direct Cost
- Assumption: Packer Bare Cost = $65/hr , Packer O&P Cost = $90/hr, Packer Operator Bare Cost = $40/hr, Packer Operator O&P Cost = $70/hr
Risk & Contingency
Total Cost
- The total cost is calculated from the O&P cost of Labour and Equipment:
- Total O&P Project Cost = $371,530.28
- % Contingency = $53,500.00/$371,530.28 = 14.4%
- Based on the risk matrix above, a contingency of 15% will be used towards the project
- Total Project Cost (including 15% contingency) = $427,259.83
Schedule
The project is expected to start on September 2nd, 2019 and completed by November 14, 2019. The project schedule can be found in the attached link provided above as a MS Project file.
Crew and Equipment Utilization
Dozer
A dozer is a crawler equipped with a blade used to push earth. It will be used on this project to spread the earth that was being hauled and to grade the surface to the correct elevation. The dozer has a capacity of 16.5 cubic meters and a average speed of 24 km/h. The dozer would require a dozer operator to operate it.
Dump Truck
Dump truck is used to haul earth material to the required fill area from the cut area on site. The dump truck has a carrying capacity of 16.5 cubic meter and an average speed of 24 km/h. The dump truck will require a truck operator to operate it.
Packer
Packer is used to to compact the earth to the correct compaction rate. The packer will need to HOW MANY TIMES DID WE DECIDE IT'S GONNA GO OVER?? Packer will require a packer operator.
Excavator
The excavator consist of a boom, dipper, bucket, and a cab. It is used to loosen material and to load the haul truck with earth material for hauling. The excavator has a capacity of 0.52 cubic meter. The excavator will require an excavator operator to operate it and a helper to with the loading of material.
Crew Utilization
- Note: Idle Resources may only be idling momentarily
- Since the utilization rate for the first 7 weeks is 55.6% (for hauling excess cut material to waste site), the dozer and packer shall be mobilized at week 7 to be used in week 8 onward.