Construction

The site is divided into 2 areas:

  1. Cut (blue) area
  2. Fill (red) area
  • Crew 1 will start at the south side of site; moving material from the blue area to the red area (indicated by the black arrows)
  • Crew 2 will move excess material from the blue area to a designated stockpile, located on the west side of site (indicated by the red arrows), which will later be hauled offsite
  • Both crews will consist of an excavator, a helper, a truck and 2 dozers
      • For jobs that only require 1 dozer, the other will be used to compact graded areas

Visit the link below to see a simulation of the construction site with commentary.