Dhillon Associates

Rehmun Dhillon, Umer Riaz, Zihan Shao, Chen Wu

Mission & Vision

Our mission is to apply our engineering expertise to deliver safe, responsive and effective solutions for our clients. By doing so, we hope to establish long lasting relationships with our clients. At Dhillon Associates, we successfully accomplish all our business challenges due to a work force motivated to succeed.

Project Background



  • To design a grading project for a high school campus
  • Project location: Guangzhou, China
  • Site area: 16770.13 m2
  • 4250 m2 to be hauled off-site


Safety Considerations




  • Staff will be properly trained
  • Standard practices to be followed to ensure safety on and around the construction site
  • Regular check-ups to be conducted on site
  • Site supervisor present at all times
  • Mandatory PPE on the construction site




Traffic Considerations




  • Reduced speed limits around the construction site
  • Temporary signage will be installed to reflect these changes
  • Extra consideration will be given during peak hours
  • Flagmen to be present for the passageway during school hours



Environmental Considerations




  • Use quieter (low-noise) equipment
  • Use absorptive materials to reduce reflected sound
  • Water truck present on site to keep haul roads damp
  • Regulate low speed on rough roads (could help reduce dust as much as 22%)



Site Layout



  • Temporary facilities will be set up
      • Project boundary
      • Site office
      • Lunch areas
      • Drinking stations
      • Washroom facilities
      • Equipment storage area
      • Temporary waste storage area

Project Schedule

The grading portion of the project commenced on Monday, September 2, 2019 and is expected to end on September 24, 2019.

Project Cost


  • Excavator productivity is the limiting factor for all jobs
  • Standby crew is not considered in cost calculations
  • Contingency is set at 15%
  • Total Bid Price = $849,429.88



Crew Utilization

  • 2 crews are required to complete the entire project
  • The entire site is split in 4 sections with each crew grading 2 sections
  • Crew 1 consists of 1 excavator, 11 dump trucks and 3 dozers
  • Crew 2 consists of 1 excavator, 12 dump trucks and 3 dozers

Unity Visualization

Dhillon Associates

Tokyo | Seoul | Hong Kong | Guangzhou | Bangkok | Kuala Lumpur
E: contact@dhillon.comP: +86 10 1234 5678F: +86 10 8765 4321

Copyright @2019 Dhillon Associates All rights reserved.