Public may experience temporary disruptions due to construction activities and on-site flagman will be assigned to ensure safe continuum of traffic flow. To ensure the continuum of traffic flow, flagmen will be directed to guide the traffic when road space is required for construction activities.
Due to grading construction activities, regular on-site watering will be implemented to ensure site material fly off (Dust) remains within the site boundaries or at minimum such that the neighborhood air quality remains impact-free.
Construction crew will only be permitted to operate during regular school hours (8:00AM - 4:00PM) in order to control the noise emissions within regular school hours.
Site fencing is designed to ensure school activities are continued uninterrupted and independent outside of site perimeter. School activities might be disrupted due to noise during site hours where school administration will be notified in advance for all possible disruptions.