Number of Excavator: 2
Number of Dozer: 3
Number of Truck: 20 (10 working 19 days, 10 working 3 days)
Project Start Time
September 1, 2019
Project Total Duration -- 19 workdays
Excavator Productivity: 76.7 m3/hr
Dozer Productivity:
124.07 m3/hr if haul distance is 20 m
34.74 m3/hr if haul distance is 80 m
Average job unit cost for 1 dozer: $5.62 /lm3
2 dozer: $5.49 /lm3
Equipment:
Grading Project need a pathway to keep school function. Node No. 22 and No.23 servers as a pathway.
Pathway is on the East Side of site, and will be grade after all grading nodes are finished.
Equipment:
Labour:
Duration: 1.9 workdays