The project is broken down into 4 main work packages:

    1. Area 1
    2. Area 2
    3. Hauling Offsite
    4. Mobilization

Each work package is broken down into job numbers, defined by different haul paths.

Area 1 and Area 2 are illustrated in the figure under "Construction"

The grading project duration is expected to be 2 months, from September 1st, 2019 to November 1st, 2019. This includes mobilization, demobilization and reclamation. Mobilization is expected to last 5 working days, while Demobilization and reclamation will take another 5 working days.

Summary of Project Duration


Click "View Timeline" to see a detailed breakdown of the project schedule: