The project is broken down into 4 main work packages:
- Area 1
- Area 2
- Hauling Offsite
- Mobilization
Each work package is broken down into job numbers, defined by different haul paths.
Area 1 and Area 2 are illustrated in the figure under "Construction"
The grading project duration is expected to be 2 months, from September 1st, 2019 to November 1st, 2019. This includes mobilization, demobilization and reclamation. Mobilization is expected to last 5 working days, while Demobilization and reclamation will take another 5 working days.
Summary of Project Duration
Summary of Project Duration
Click "View Timeline" to see a detailed breakdown of the project schedule: