This feature enables you to bind or unbind a milestone that had previously been bound to the project with the requirement in question.
Prerequisite: Milestones must be 'Active'
Select the requirement you want to work with
Click on the 'Milestone' tab
Click on [+]. A pop-up window 'Choose milestone(s) to bind to requirement' opens :
Select the milestones you want to work with
Click on [Confirm]
Select the requirement you want to unbind
Click on the 'Milestone' tab
Select the milestone(s) you want to unbind and click on [-]
Click on [Confirm]
FOCUS
The disassociation can be performed in a unitary manner by clicking the [-] button located at the end of the milestone to disassociate.
The creation of a requirement in a project in 'Milestone mode' automatically associates the requirement to the milestone that has been selected for the 'Milestone mode'. If you wish to do this, please follow these steps:
Prerequisite: Milestones must be 'Active', and the 'Milestone mode' must have been ticked in the library (2.01 - Library functions)
Go to the Requirement workspace.
Select a project, a folder, or a sub-folder by clicking on the name of the element. It will be highlighted.
Click on [Create] in the library toolbar . A drop down menu is unfolding. Click on [New requirement...]:
A pop-up window « Add a Requirement » in which you can fill in different fields shows up. The field "Name" is the only mandatory field.
Click on [Add] if you want to add only one requirement or click on [Add another] if you want to add several requirements at the same time.
The new requirement is displayed in the project’s tree structure, under the previous branch which was just created in the project. In order to organize the requirements in alphabetical order, it is necessary to refresh the page using [F5]. The requirement is automatically bound to the milestone selected for the 'Milestone mode'.