Starting to think Bigger thoughts - leads to Steven's, Hollands Boat House, Evelyn Anderson House, wood floor in Lodge, Chadwick renovation
Educate Dan on B/G situation so he can prioritize with the board.
Dan would like to Plan more rather than fire fighting of the current needs only.
Dan would like to get to a goal of a yearly report of:
every buildings detailed information – needs, current status, plans
Infrastructure current status, needs, plans
Long term needs
Daily needs
Has high expectations of what we can do to make camp better and more functional and will work towards these goals as time goes on. Dan will work with Butch more as he learns the situation and Butch’s tasks at hand.
10 year plan to maintain
Marcus set 3 year plan with board
1) new docks, finish upper Leining new rooms, bathroom - should all be done 2006
2) Lodge Furniture
3) Zigmund expansion and move
LODGE:
….Lodge floor is new plan, chimney forward (ping pong room not covered in this plan),
plywood subfloor with ¾” oak flooring, sealed with linseed oil, no finish on top.
Chimney can still leak around edges. Plan in hand is to box in chimney with traditional
framing, flashing with the smoke pipes sticking through top of framed box.
Flashing between ROCKS and the wood deck has NEVER been successful. Flat
traditional walls and roof deck should Flash perfectly.
Door molding never installed or not proper throughout lodge, screen door on front porch
door is gone and might be nice.
Carpet replacement is priority – has to be done properly with the proper carpet. Existing
carpet has lasted 23 years and no seams are showing and no part is worn through!
New furniture, cabinets/shelves in lower lodge, Paint lower lodge walls,
Higher end maintenance – Cleaning of Globes, fan, high windows. Pressure washer will
be tried in cleaning upper windows on the outside.
Rear wall needs to be painted/sealed with black paint – oil mixture…
Piano can be removed parts recycled wood can be burnt
General cleaning to a higher standard
Ping pong table new parts needed or new legs built
Lower bathroom needs to be gutted and redone as part of overall lodge make-over
New wood stove for lower lodge
New windows are needed with screens… to replace windows that do not close, lack
screens and are in poor condition. – Phil Lewin window contact
Certain furniture pieces will stay, including hand-made bench on front, large Kings chairs
in good shape.
Program office better chairs, wire to computer needs to be rerouted.
Gutters need to reach ground with possible underground pipe run-off system like Gilman’s
Lightning rods on lodge
Rails on back porch need replacement
Ground off screen porch needs to be raised with timbers at step and filled in with sand.
Sweet:
Removal or trimming of bushes around building.
Floral park – Oneonta bathroom When new drywall is installed reconfigure bathrooms
so each cabin has toilet/sink. Devin had a drawing for plan.
Upper bathroom floor needs to be ripped out, new subfloor laid down as needed and new
tiles 100%.
Pressure on water cuts out 100% in sweet at times.
Fire escape needs replacement
Screens to the windows that are marked fire escape do not open OUT , HOOK latches are
on windows, latches that PUSH open are needed, NO hooks should be present
Leining,
Nurse bathroom is Marked EXIT form the infirmary, Nurse can LOCK her bathroom
door thus not allowing exit access. NOT proper EXIT pathway.
GILMAN
Walk-in cooler is dripping water, need to ask Dan Covey from Lowville what is wrong
appears to be condensation runoff not going out he drain pipe
Lightning rods needed
New stove needed
Benches in horse need paint rail at horseshoe needs replacement
New windows are needed in dining hall so the work .
Lake side walls needs rough cut siding
Questions for kitchen> Dishmachine – can it be made to wash dishes well? Is new mixer
needed?
NEEDED:
NEW STOVE commercial heavy duty grade, 10-12 Large size burners
Robo food processor needed
Flash heater for dishwasher could be a problem clean or replace??
Playground, simple play stuff is needed
Showerhouse,
Woman’s paint floor, walls, new toilet dividers (hiney hiders brand like boys side)
Tile replacement in shower #2, shower head replacement in 2 showers,
Ceiling built in,
New washer and dryer needed for laundry
NOTE leining has hookup for washer/dryer in lower Leining!!
Boys side, paint floor
Water pressure and temp fluctuates in womans side to a large degree, as other sources
come on and off.
Overlook
Lower right Molding on doors
Lower Left, new bathroom, configuration using the closet – shower?
TANK for propane by shower house should be looked at close by propane company,
maybe a new one is safer as it is old and rusty a bit.
Zigmund plan a new configuration and move away from Chadwick and build addition
Septic Lid in front of Smith needs to be covered or removed in some way
Lean-to remove barrels replace roof save a few barrels under shop for emergency use.
Boathouse jack posts 2 are needed for center beam
Artshop flasheater not working not wired,
Trees in upper camp can be trimed up to allow sight lines Lodge to Overlook etc.
Trees along Hill be Gilman to be cut back/down to allow look at lake.
Waterfront, rebuild docks in proper configuration.