اهداف و مشخصات میدان گازی تابناک

Specification and Objective

The project is comprised of drilling 19 wells plus two work overs.

The parties of the project is Consortium (A few Chinese companies under management of China National Petroleum Co. and Bonyad Machine Co.) acting as the contractor and PEDEC as the client.

Supervision of the contract was delegated to Naftkav after 8 wells being completed under KEPS (former Supervision Company) Supervision

Project was handed over to Naftkav @ April 21, 2003

Naftkav is responsible for technical supervision of drilling 8 wells and finishing three incomplete wells

Six of these wells will be drilled in Tabnak as development wells, the two others will be drilled in Homa field as appraisal wells

The project staff is comprised of 34 Specialists in Drilling, Geology, Completion, Logistics and related administration activities

The best record ever made by Consortium was achieved under Naftkav supervision. The well was completed in 57.5 days.

The applied discipline by Naftkav management caused a considerable improvement in the relation between Consortium and PEDEC