LOCATING AND CONTROLLING WATER PRODUCTION IN HORIZONTAL
LOCATING AND CONTROLLING WATER PRODUCTION IN HORIZONTAL
WELLS (PERMIAN BASIN)
Andrew V. Padilla
Chevron U.S.A. Production Company
Midland, Texas
Jay Miller
TAM International, Inc.
Houston, Texas
ABSTRACT
Applying horizontal well technology to improve oil recovery in reservoirs undergoing active water
flooding continues to evolve with improving success. Development of remaining unswept oil
reserves with horizontal wells as a method to improve conformance is a significant challenge.
Evaluating and optimizing well performance to achieve economic results in a waterflood setting is
a critical step in maximizing the success of a horizontal well project. Horizontal laterals expose
large amounts of productive reservoir rock, benefiting certain reservoir applications while adding
a major risk component to well designs planned for heterogeneous, water flooded carbonate
reservoirs. Long laterals increase potential of exposing undesirable geologic conditions such as
water-filled fracture networks, zones of high water saturation and extreme permeability of thief
zone intervals. A significant negative impact on well performance from high water production
rates can result in lower oil rates and excessive lifting costs. This paper summarizes methods
and experiences in mechanically evaluating and diagnosing fluid entry in newly drilled horizontal
wells, efforts and results to control water entry and optimize well performance. Also discussed
are field test results of a new tool design combining re-settable, inflatable packers and a hydraulic
jet pump. Early field test results suggest this method will be a promising advance toward efficient
diagnosis of fluid entry in both vertical and horizontal wells.
INTRODUCTION
Efforts to evaluate the potential benefits of horizontal wells to develop unswept oil reserves began
in the McElroy field in 1995. Initial horizontal well results in this mature waterflood were
encouraging but began to reveal a major problem with excessive water production. The
horizontal producing wells designed to avoid water cycling conditions were encountering geologic
and reservoir features that resulted in high water cut production performance
. Basic horizontal
well design in McElroy was a re-entry of an existing vertical wellbore and drilling medium radius
lateral(s) with 4 ¾” open hole completions
. Designs included 600 to 1000ft laterals drilled at 2 to 5
degrees from true horizontal to expose multiple layers of an overall 30 to 40 ft thick target zone.
(Figure 1) A major challenge was to understand the true impact of horizontal producing wells in
this waterflood setting which required some degree of evaluation to determine a fluid entry profile
over the length of lateral and build sections. Neither practical nor effective logging procedures
were available for wells requiring artificial lift methods, thus mechanical isolation and short term
swab testing was utilized to understand fluid entry and to explain well performance. Inflatable
packers are an integral component in the evaluation design due to the nature of the open hole
conditions. Large 200 to 600 ft long sections of the laterals were isolated independently using a
bottom inflatable bridge plug and an upper inflatable production packer. Swab testing or short
term full drawdown production testing provided a basic indication of fluid entry rates and oil cut.
After moving inflatable equipment and testing various portions of the open-hole wellbore, a
completion design using inflatable isolation assemblies were used to exclude zones of excessive
water entry and optimize oil production. Basic test objectives have remained the same over the
past 4 years, however the equipment and methods have evolved to reduce costs and improve
accuracy and efficiency.
Continued development of inflatable tools and production testing methods resulted in recent tests
using a new approach to improve fluid entry testing process. Re-settable inflatable straddle
packers combined with a hydraulic jet pump provide full drawdown testing on short intervals. This
new method allows for testing multiple zones under full artificial lift drawdown with a single trip in
the hole. Initial field trials demonstrated a major advance toward improved efficiency and
reduced cost of evaluating well fluid entry.
EARLY EVALUATION METHODS
Initial production testing of newly drilled horizontal wells with the full length of the curve and
lateral exposed frequently showed surprisingly poor results. Swab testing before the initial
completion regularly showed 100% water production. Swabbing rates were not sufficient to draw
the fluid levels down in the well due to high formation productivity. Initial tests using electric
submersible pumps as the artificial lift method showed low oil cuts, high fluid levels and water
rates 2- 5 times that of surrounding vertical producers. Wells that showed some or complete loss
of circulation while drilling (fresh water drilling fluids with reservoir pressure of 600 – 800 psi)
were typically the worst performing wells during initial testing. Drilling data and initial testing
observations clearly indicated problems with undesirable water entry along the lateral portion of
the well. A mechanical isolation and swab test procedure was designed to determine if the
zone(s) of excessive water entry could be located. Inflatable packers were used to provide
isolation, and swab testing was used to determine fluid entry rate and oil cut. A very coarse
evaluation with three intervals, the curve and two segments of the lateral was the typical design
that met testing objectives at acceptable levels of cost. The zones at which lost circulation
occurred during drilling sometimes dictated how the lateral would be segmented for testing. Mud
log data, drill rates, lithology, and oil fluorescence data was also regularly used to pick packer
seats and assist in test zone determination.
Setting inflatable packers in this process proved to be relatively simple and reliable in the open
hole. Inflatable packers used as bridge plug were configured with bull plugs and on/off tools to
allow for disconnecting and retrieval. Retrieval has been 100% successful. Inflatable production
packers were re-settable to allow for expanding or reducing the test interval if necessary. Once
packers were installed, swab testing was expected to be ideal for obtaining simple and effective
results. Although swabbing proved to be a low cost approach, it was found inaccurate and
misleading. In wells with low reservoir pressure and/or high inflow condition, swabbing was not
effective in creating sufficient drawdown to achieve inflow from tighter oil bearing zones. Oil cut
results were often pessimistic with only traces or no oil shows present. At best, swabbing proved
to be a good indicator of the water entry zones when the fluid level could not be pulled down. The
potentially productive intervals were readily recognized because they could be swabbed down to
various degrees and often showed 5 – 20% oil cut during swabbing. This method of evaluating
fluid entry was slow, expensive, and was not successful in achieving accurate and definitive
results. It did however, prove to be a highly valuable step in a successful well project. The
qualitative findings were able to show oil production that was not present during initial well testing.
It was able to provide important information resulting in improved decisions on the productive
potential of a well, and the feasibility of further investment.
Typical testing by this method took up to 1-2 days per test interval and frequently required 10 to
12 days of rig time to complete a cursory evaluation the well.
A MODIFIED APPROACH TO FLUID ENTRY EVALUATION
Because of shortfalls in swab testing method, the testing procedures were modified in two basic
ways. First, individual zones were tested for extended periods using ESP pumping equipment to
achieve full drawdown. Secondly, test tool configurations were designed with straddle packers,
seating nipples and sliding sleeves so that fewer packer sets were needed to accomplish the
testing plan. The use of submersible pumps with variable speed drive units provided good
flexibility to test zones with different inflow performance at full drawdown conditions. The duration
of ESP tests were lengthened to ensure valid, stabilized oil cut results. Although test results
improved significantly, frequent pulling and re-running ESP pumping equipment was time
consuming and expensive. (Figure 2) summarizes a case history for this type evaluation.
Re-settable, inflatable, straddle packer systems were also introduced into the testing efforts and
provided a process to test multiple zones without pulling out of the hole to redress tools and
packers. (Figure 3) A packer spacing of 200 ft was used. Swab testing each isolated interval
was again attempted as the necessary way to determine fluid entry and oil cut. Straddle packers
worked quite well in improving the efficiency of isolating different zones and allowing for a more
complete wellbore evaluation. Although the desired results of efficient multiple tests was
achieved, swab testing again proved inaccurate and generally prolonged testing efforts. This
evaluation method showed excellent potential in wells where swab testing would be effective.
Depending on the length of the lateral and the desired test information required, spacing could be
lengthened or shortened. A typical test could result in 10 to 25 zone tests with good wellbore
conditions. These modifications in testing methods and tools began to solve many of the
problems encountered, but there still had to be a better process to meet all the objectives.
The inflatable packers overall, performed well in achieving competent hydraulic seals in the open
hole. The Grayburg reservoir is a dolomite formation with good compressive strength. Some
difficult hole conditions were encountered (i.e. oval hole, key seats, and washouts), however most
wellbores were found to be competent, gauge and suitable for trouble free testing. Packer setting
was generally reliable with few function problems and element failures were rare. Use of different
setting mechanisms as well as new element technology improved tool reliability. Because packer
seats cannot be pressure tested on open hole situations, a practice of picking up and slacking off
10,000 lbs was adopted to help verify solid packer seats. Fluid movement through the nearwellbore
area, around the 4-foot packer elements has not been recognized as a problem.
MECHANICAL WATER SHUT-OFF COMPLETION OPTIONS
Once water entry and oil productive intervals were delineated, three basic completion designs
were used to control water entry. The type of mechanical control device depends on where the
water is found in the lateral. Water found at the toe can be controlled by an inflatable bridge
plug/cement retainer. (Figure 4) Water production found in the lateral can be controlled by a scab
liner. (Figure 5) Water production found in the toe and heel of the well can be controlled by an
inflatable bridge plug/cement retainer at the toe and a scab liner in the heel. (Figure 6)
TESTING OF THE JET PUMP STRADDLE PACKER METHOD
A reliable, re-settable test tool including an artificial lift method was required to determine a
producing profile and make water shutoff decisions. The simplicity and reliability of a hydraulic jet
pump were coupled with inflatable re-settable straddle packers. The ultimate intended use of this
tool was to test open hole horizontal wells, but the initial well selected was a vertical cased hole
well with multiple perforations.
The tool string was configured with three packers and a jet pump. (Figure 7) The bottom two
packers isolated the test interval and the top packer isolated perforations from the produced and
power fluid returns producing up the casing annulus. The jet pump is placed in the string just
above the top packer. A remote setting head above the jet pump and inflatable packers is
connected by a ¼” stainless steel inflation line, insuring that all three packers function
simultaneously.
Once the tool string is made up, it is lowered to the desired set depth. The jet pump is pumped
from the surface to the carrier and is seated. Continued pumping results in increased tubing
pressure and is held at approximately 800 psi to inflate the packers. Simply slacking off on the
work string traps inflation pressure in the elements. Continued tubing weight is applied during this
test.
Power fluid rate and pressure to the jet pump are adjusted to establish drawdown and production.
Power fluid along with produced fluid return to surface via the tubing-casing annulus. Both power
fluid and produced fluid rates are measured with the difference equaling production rate. If no
extra fluid is produced, then that zone is deemed nonproductive and the tools are moved. If the
hole is full, casing volume is calculated to determine when actual bottoms up fluid can be
expected at the surface. For the McElroy tests, produced fluid was calculated to reach the surface
in 1.5 hours. Bottoms up fluid is not necessary on all tests to determine fluid entry and production
rates, but is necessary if oil cuts are to be determined. If the produced rates are low, the
perforations can be grouped in later tests to obtain good oil cut data. If the hole is empty, bottoms
up fluid will be the first produced.
After testing each zone, moving tools to the next test interval required less than 30 minutes. The
only difficulty encountered while restarting a test, was a loss of blanket gas in the test separator.
Care should be taken to assure that all valves on the surface equipment are closed when moving
tools.
The initial intent was to test the tool configuration and workability in a vertical well before running
in a horizontal well. After experiencing the effective and reliable tool function, seeing the quality of
the test results and the ease of obtaining them, this method of testing was deemed very
applicable to testing vertical cased hole wells.
Acidizing during the test procedure can be done without pulling the tools. The jet pump is
removed and replaced with a blanking sleeve, test zone stimulated, sleeve pulled and jet pump
replaced. Spent acid is then produced and the zone re-tested.
JET PUMP DETAILS
Jet pump offers several advantages as the artificial lift means. A wide range of test rates can be
achieved with one pump size. The pump size can be easily changed to match the well production
and a broad range of jet pump sizes is available. The pump can be easily removed from well by
reversing it out of the hole or pulling it with the sand line. Inefficiency in power fluid use is not a
problem during short duration tests versus running the pump for a permanent artificial lift
application. Power fluid can be oil, field water, produced water or any readily available,
compatible fluid.
SURFACE EQUIPMENT
•
Portable test separator for fluid handling.
•
A propane tank to supply blanket gas pressure for instruments and fluid dumping on wells
producing low gas volumes.
•
A pump and filter with output of 1.5 bpm at 3000 psi. In this example, the available workover
rig pump was used.
•
Storage tanks for power fluid, produced water and produced oil.
Testing was initiated with 100 bbs of field salt water in a 500 bbl tank. Separate oil and water test
tanks made measurement of produced fluid easy and accurate. Flow meters could be used,
however the tanks provided simple, inexpensive and accurate results.
JET PUMP TESTING IN HORIZONTAL WELLS (Planned for February 1999)
To test in horizontal wells no modifications to the tool string are needed. (Figure 8) The lower
inflatable straddle packers are spaced out with tubing and perforated pups to cover the desired
test interval. Spacer pipe is attached and spaced out so the upper packer can be set at the
bottom of the cased section of the well. As before, the jet pump is attached in the string just
above the top packer and the remote head just above it. The remote head and all three packers
are connected by ¼ stainless steel tubing again assuring that all or none of the packers is set.
The stainless steel control line is placed inside the tubing in the horizontal application to guard
against damage from rubbing when running into the lateral.
One potential problem with this simple tool configuration is that each time tools are moved, the jet
pump is moved higher in the vertical well reducing drawdown capacity. This results in a higher
chance of pumping off that test interval. If the pump were on top of the two packers comprising
the straddle interval, this would not happen. With the simple system, the tool string must be pulled
and the spacing between the lower straddle and upper packer reconfigured to optimize drawdown
capacity.
A modified horizontal well test tool is in development utilizing an inner string hung off in a
crossover head just above the upper packer and containing the jet pump positioned immediately
above the test interval. Power fluid is pumped down the inner string, produced fluid and power
fluid are returned up the annulus between the tubing and the inner string until it reaches the
crossover above the upper packer. Total fluid flows through the crossover hanger into the tubing -
casing annulus and to the surface.
This system, positioning the jet pump on top of the straddle packers in the lateral (Figure 9)
provides maximum draw down capability for all tests of the lateral. This method will be the
primary test method in the future and both provide major cost and time savings over previous
methods used.
Pending completion of proposed well work, results of the horizontal tests will be presented in April
at the SWPSC.
CONCLUSIONS
An accurate and cost effective method to diagnose water entry in horizontal wells is necessary to
verify and optimize successful well projects.
Mechanical water shut-off methods can be very effective in controlling unwanted water production
in horizontal wells. Successful results can be achieved at a reasonable cost.
Inflatable packers used for selective open hole testing applications have proven reliable and
effective. Improvements in inflatable element design have greatly increased their reliability in
multiple set, open hole testing operations.
Jet pumps provide an artificial lift method that is flexible and effective in varying inflow rates at full
drawdown conditions.
Multiple set inflatable straddle packers and jet pump tool combinations can drastically reduce
testing cost and provide for a more detailed and thorough testing information in both horizontal
and vertical wells.