Review the certificate of conformance for the charger from the manufacturer to ensure that the charging equipment has at least 2 low levels of control or confirm that no charging of the battery will occur at Nanoracks.
Evidence:
Review team registry to confirm activities are student led.
Evidence: https://sites.google.com/site/manitobasat1/mission-objectives-1/team?authuser=0
Review documentation to confirm import confirm that any ordered GSE are not ITAR controlled .
Evidence:
Review documentation test to confirm test duration of 120 seconds per axis.
Evidence: https://sites.google.com/site/manitobasat1/subsystems/ait/phase-d-build-and-test-plan/spacecraft-level-testing-and-shipment?authuser=0
Review documentation to confirm hard mount configuration is used.
Evidence: https://sites.google.com/site/manitobasat1/subsystems/ait/phase-d-build-and-test-plan/spacecraft-level-testing-and-shipment?authuser=0
Review documentation to confirm test has Maximum Expected Flight Level of +6dB for a duration of 120 seconds per axis.
Evidence: https://sites.google.com/site/manitobasat1/subsystems/ait/phase-d-build-and-test-plan/spacecraft-level-testing-and-shipment?authuser=0
Review Thermal Vacuum Chamber documentation to confirm that it has the necessary specifications.
Evidence: Figure 4 shows TVAC specifications confirmed by Magellan https://sites.google.com/site/manitobasat1/subsystems/ait/ait-facility-and-gse
Review that test equipment meets 2.0 m/sec^2 environment.
Evidence: https://sites.google.com/site/manitobasat1/subsystems/ait/ait-facility-and-gse?authuser=0
Review system level test plan to confirm 2.0 m/sec^2 load environment test.
Evidence: https://sites.google.com/site/manitobasat1/subsystems/ait/ait-facility-and-gse?authuser=0
Inspect the fully assembled spacecraft at the end of AIT activities to ensure that the inhibit switches are engaged.
Evidence:
After all testing in completed, Inspect deployables (Solar Arrays and Antenna) to confirm they are in the stowed position prior to beginning packaging.
Evidence:
Review required training and documentation for team members responsible for integration have received electrical bonding training to confirm they understand SSP 30245 Rev. E procedures.
Evidence:
AIT soldering activities shall use material outlined in SSP 30245 Rev. E.
Evidence: https://sites.google.com/site/manitobasat1/mission-objectives-1/team?authuser=0
Review FlatSat test design to ensure that when the RBF is engaged, the only electrical source will be umbilical battery charging.
Evidence:
Inspect the ManitobaSat-1 after AIT activities to ensure that the RBF pin installed and the power system is non-operational.
Evidence:
Review documentation to ensure that test axis orientation is consistent with Nanoracks orientation system.
Evidence: https://sites.google.com/site/manitobasat1/subsystems/mechanical-structural/structural-icd-overview?authuser=0#h.p_2EMN9MtgbmKs
AIT activities shall take place inside a clean room of minimum rating 100,000.
Evidence: https://sites.google.com/site/manitobasat1/subsystems/ait/ait-facility-and-gse?authuser=0
Inspect AIT area to ensure that the minimum distance between CubeSat and EGSE is 2 metres.
Evidence:
Inspect the facilities to ensure that at minimum two assembly tables are available.
Evidence: https://sites.google.com/site/manitobasat1/subsystems/ait/ait-facility-and-gse?authuser=0