To duplicate the final estimate:
Navigate the folder structure and locate the correct project.
2. Right-click the final estimate to be used as the construction estimate and select "Copy"
3. Right-click again and select "Add Cut/Copied Row(s).
4. Enter the project name and number:
Project Name = Construction Estimate to end of the project name
Project Number = First, middle, and last name initials of the PM and the award date in YYYYMMDD format, space, and CE for construction estimate.
5. Be sure the "Copy Job" checkbox is checked.
6. Be sure all components are checked.
7. Select OK
⚠️
Note:
Accubid Anywhere does not allow (2) [Projects] with the same name or number and (2) [Estimates] with the same name or number. (see screenshot below).
Be sure all checkboxes are checked. If any are unchecked, this construction estimate will not match the final estimate.