To create an approved change order:
1. Go to the CO tab
2. Either select "Add" from the ribbon or right-click, and select "Add."
3. Enter the Change Order# = Customer’s change order number
4. Select the drop-down arrow in the PCOs field.
5. Select the approved PCO(s) = Check the applicable PCO(s)
6. The [Subject] field automatically populates. However, the subject can be overridden. This can be used when multiple PCOs are approved with one CO.
7. GC Number = Enter if you have a GC number
8. CO Date = Enter the change order approval date
9. Start Date = Enter the start date for the approved work
10. Received Date = Date received go-ahead for the work
11. Value = Selling price of the PCO
12. Client CO # = Customer’s change order number
13. Close the dialog box.