This screen contains tasks/% of hours performed by field or shop personnel above and beyond the direct installation of materials.
⚠️
The preferred method of labor factoring an estimate is to apply a factor in one of the Takeoff Breakdowns. By applying a factor in the takeoff; Extension hours will reflect the factored value. This is especially valuable when completing a Start Point form.