1. In Breakdowns: change the Bid Item, Drawing, Area, and Phase as needed. Select Systems – 210 Network Cable System. Select the Takeoff Task – Horizontal Distribution.
This sets the appropriate specification and Takeoff Pad.
2. Ensure the correct Attributes are selected.
3. On the Takeoff Pad, click the single-cable generic network cable drop icon.
4. In the assembly menu:
Populate all required fields below.
Enter Count = 1
5. Hit [Enter] on your keyboard or select “OK”.
6. Click the “+” to view the results of the takeoff.