Backup Gateway Guts
WiFi Antenna
Communication Connectors
Reset Button and LEDS
Ethernet Port
Meter Y (Extra CT ports)
6. Non-Backup Lugs
7. Neutral Bonding Straps
8. Neutral Lugs
9. Load Side Backup Lugs
10. Meter X (Internal CTS)
11. Supply Lugs
A. This is where the Supply Breaker (Main breaker goes)
12. Ground Bar
**Key Points**
The Backup Gateway 2 functions as an automatic transfer switch to manage a residential electrical system.
It can disconnect all downstream loads from the grid and signal the Powerwall to create a microgrid.
Systems can be configured for either whole-home backup or partial-home backup.
Large loads, such as water pumps and air conditioning units, can be excluded from the backup circuit.
The internal panelboard kit is an optional accessory that eliminates the need for a subpanel.
The Backup Gateway can serve as the main service disconnect for the site when used with an Eaton CSR or BW breaker rated between 100-200 Amps.
The neutral bonding strap must be removed if the Gateway is **not** acting as the main service disconnect.
The non-backup lugs support up to 100 amps.
Meter X has embedded CTs that measure the supply feed.
Meter Y uses 100 Amp Auxiliary CTs and can be used for monitoring solar, site loads, or conductor performance.
A low-voltage switch (RPSD) can be installed to disable all Powerwalls paired with the Gateway.
METERING
Site Metering using Built-in CTs
If the Backup Gateway 2 is installed at the service entrance (upstream of all loads), the built-in site metering functionality is used. No additional metering hardware is required for measuring site-level power flow. If the Backup Gateway 2 is downstream of an electrical panel, Auxiliary CTs or a remote meter are needed to monitor the utility connection.
An external meter is required if more than three Auxiliary CTs are needed, or if conductors that need to be monitored are beyond the 330 feet reach of the Gateway.
If wiring splice is needed the we need to use 20ga 600v wiring.
Auxilary CT metering
Plug the Auxiliary CT connector into the port at the top of the unit.
Keep in mind that the left most port is L1, the middle is L2, and the rightmost is L1.
Things to Look out for when installing and auditing
Metering is critical to the function of the Powerwall system
The Backup Gateway contains two meters.
Meter X monitors the supply connections through embedded CTs
Meter Y can be configured to monitor various sources with Auxiliary CTs.
Site, Solar, Solar 1x2, Conductor, or Load Monitoring is available
Auxiliary CTs can be extended up to 330ft
Auxiliary CTs are rated up to 100 Amps.
Auxiliary CT ports default to L1, L2, and L1 respectively.
Always plug CTs into the port at the Gateway before clipping them around a de-energized conductor.
If Meter X and Meter Y cannot monitor the entire site, a Remote meter will need to be added.
Auxiliary Meter Y equipment is NOT cross compatible with Remote metering equipment.
Note: that Auxiliary Meter Y equipment is NOT cross compatible with Remote metering equipment.
Confirming
Power factor can be examined on the CT page of the Wizard. Review Power Factor to confirm that CTs are installed correctly. It is strongly advised that you observe Site CT readings without the input of energy from PV systems, so leave PV systems off until you confirm that Site CTs are installed correctly. To review Power Factor toggle the "Advanced Slider" on the CT page.
Note: Installers can run a heavy load (like a plug in drill) to confirm the CTs are performing correctly
Generation Panel
The Backup Gateway comes with 2 sets of backup termination lugs, and one set of non backup termination lugs. These lugs can be used to feed new or existing downstream electrical panels.
One set of lugs can also be used to feed the optional internal panelboard kit, removing the need for a subpanel.
Solar and Powerwall can be added to the generation panel downstream of a 200A disconnect. NEC article 705.12 (d).
TYPICAL WHOLE HOME BACKUP SET UP.
TYPICAL PARTIAL HOME BACKUP
HOW THE ONE LINE SHOULD LOOK LIKE FOR A WHOLE HOME BACKUP.
HOW THE ONE LINE SHOULD LOOK LIKE FOR A PARTIAL HOME BACKUP.
Neutral Bonding Strap
If the Gateway 2 is acting as the main point of disconnect, keep the neutral bonding strap in place.
Remove the neutral bonding strap if the Gateway 2 is installed downstream of the main disconnect.
Integrated Tesla Metering
Gateways need to monitor the following:
All energy flowing from the utility meter.
All solar generation
Downstream generators if applicable
Conductor export limits if applicable
In most cases, site energy flow will be monitored by the embedded Meter X CTs, and solar inverters can be monitoring with the Auxiliary Meter Y CTs. Energy metering will be covered in depth in later trainings.
PARTS
Included Parts
Owners guide
Service disconnect label
Single 100A CT
Single CT extension
Sealed washers for mounting
Optional Accessories
Additional 100A auxiliary CTs
10ft Auxiliary CT extension cables
2" Top entry conduit hub
1 & 1/4" Top entry conduit hub
Internal panelboard kit
Optional Internal Panelboard Accessory
The internal panelboard accessory can be installed inside of the Gateway 2 and removes the need for a subpanel to house generation sources or relocated non-backup loads. The Panelboard can be configured to the line or load side of the relay (backup or non-backup).
6/12 Space Eaton Type OPD
200A capacity for Backup
100A capacity for Non-Backup
Note: The panelboard must be used exclusively for backup, or exclusively for non-backup.
Take the deadfront off the front of the Gateway
Determine whether cable entry to the Backup Gateway will be from the top, bottom, rear or side of the enclosure. Knockouts are 3/4" trade size and can be expanded up to 2".
NOTE: If we need to configure the Backup Gateway for cable entry from the top, do the following:
Remove the top entry plate.
Install the 2" or 1 & 1/4" top entry hub with the included screws.
Use a reducing bushing if your conduit is smaller than the hub
Install the (4) mounting screws into studs that can support the weight.
Dimension of the Gateway
Mounting diagram
Semi-Flush Mounting
The Backup Gateway 2 can be semi-flush mounted, with a maximum depth of 4.25". This is to ensure the door swing does not interfere or contact the mounting surface.
ELECTRICAL
Note: When wiring the unit, work from the back of the enclosure towards you. This will make it easier to land conductors and cleanly route them through the unit. Plan your conductor routing to avoid difficult wire bending.
Wiring Diagram
Connect the supply conductors to the Backup Gateway Supply terminals or main breaker if present.
Connect the home load panel conductors to the Backup Gateway's Backup Terminals
For partial home backup with Non Backup loads under 100A, a Non-Backup panel can be connected.
Optional Panelboard Kit
The internal panelboard kit may be installed in the Backup Gateway 2 and connected to either the Backup side or to the Non Backup terminals by feeding a two pole breaker on the bussing.
Mount the internal panelboard using the provided mounting screws.
Breakers in the Backup Gateway has a breaker hold down kit.
Backup Wiring
The included jumpers will block the outer L1 and L2 load side lugs once installed. Be sure to land and torque all other backup conductors before installing the jumpers. It is recommended to phase tape the jumpers.
Note that the jumper wires cross over, which makes the first breaker space L2. This is indicated on deadfront's diagram.
Panel board Diagram
Panel Board wiring diagram
2p breakers and breaker hold down kit.
If the Gateway is the main point of disconnect (disconnect from the grid)
Install Main Breaker in the supply side lugs from the approved breaker list
Non-Backup Wiring
If using the Panelboard for non-backup loads, connect the non-backup lugs to an Eaton Breaker (up to 100A) on the bussing. The kit does not include pre-made jumpers. SO the installers will need to install wires that comply with NEC 310.16
Key Points to remember
Do not flip the Gateway 2 or it's internal components.
Top entry requires the use of a Tesla conduit hub.
Remove the bonding strap if the Gateway is downstream of the main service disconnect.
Refer to the chart on the back of the deadfront for torque specs and wire gauges
If using the panel board kit, be sure to land and torque conductors on the outer lugs before installed the feeder wires to the panel board.
Do not run wires across the middle of the unit
Fabricate and install the Powerwall communication connector