This Guide will help you with installing multiple CTs for situations (Shown below) when you can't capture all the loads with just regular CT installation practices.
This guide expands on the standard SolarEdge instructions for configuring a consumption meter using parallel CTs, most commonly required when a home has dual main service conductors or multiple parallel feeders that must be measured as a single load.
Parallel CT configuration is used when:
The home has two or more main service conductors supplying the same load (dual mains, split services, parallel feeders).
Total site consumption must be measured accurately as a single value.
A single set of CTs cannot physically or electrically capture all conductors.
By installing matching CTs in parallel, the SolarEdge consumption meter can sum the current from multiple conductors per phase.
SolarEdge Consumption Meter (Revenue Grade or Inline, as specified by the project)
One additional identical set of CTs (for a total of two CTs per phase)
CTs must be the same part number
⚠️ Important: Mixing CT models or ratings will cause inaccurate readings and is not supported.
❌ PCS / BCM (Power Control Systems / Busbar Current Management)
Parallel CTs cannot be installed on SolarEdge meters used for PCS/BCM functionality.
Before installation:
De-energize equipment when possible and follow all local lockout/tagout procedures
Verify conductor identification (L1, L2, Neutral)
Inspect CT wiring insulation and connectors
Always follow NEC, AHJ, and utility safety requirements.
Each phase (L1 and L2 in split-phase systems) will use:
Two CTs installed on two separate main conductors
For Lug fed panels that only place to install the CT is on the sub panel feeder wires, the L1 and L2 on the main part of the bus should go through the respected L1 and L2 CTs
The secondary CT are wired in parallel back to the SolarEdge inverter
This allows the meter to read the combined current as if it were a single conductor.
Install inverter(s), production meter, and communication components per standard SolarEdge procedures
Verify system powers up correctly before installing consumption CTs
For each phase (L1 and L2):
Install one CT on each conductor of the same phase
Ensure:
CT arrow or label points toward the meter
Both CTs for that phase are oriented the same direction
⚠️ Incorrect orientation will cause negative or reduced readings.
Maintain strict phasing discipline:
L1 CTs → L1 meter terminals
L2 CTs → L2 meter terminals
Do not mix L1 and L2 CT wiring
⚠️Mismatched phasing is the most common cause of inaccurate consumption data.
For each phase:
Connect the same-polarity CT leads together:
S1 → S1
S2 → S2
Land the combined conductors into the appropriate meter terminals in the SolarEdge inverter
Guidelines:
Use proper wire nuts, ferrules, or terminal blocks
Keep CT wiring twisted and neatly routed
Avoid sharp bends or pinched insulation
In SetApp or inverter configuration:
Set meter role to Consumption
Select correct:
Grid type (Split-phase)
CT rating
Confirm consumption meter is enabled
No special software setting is required specifically for “parallel CTs”—correct wiring is what enables summation.
After installation:
Power up system
Confirm meter is communicating
Verify no CT or meter faults
Turn on known loads (HVAC, oven, dryer)
Confirm consumption increases appropriately
Compare readings against utility meter if possible
Negative consumption values
Consumption roughly half of expected
Erratic or zero readings
Label CT leads (L1-A, L1-B, L2-A, L2-B)
Take photos before closing panels
Document CT ratings and part numbers in job notes
Verify readings before leaving site