This SOP outlines the required steps and quality checks for auditing SpS tickets. SpS audits follow the general auditing workflow but require additional attention due to unique scopes of work, jurisdictional requirements, and code-critical tasks.
General Audit SOP: LINK
Ground Mount Installation Audit Training: LINK
Retrofit / Structural Reinforcement Training: LINK
Always review the service ticket notes
Confirm the full scope of work assigned.
Check for jurisdictional requirements, contractor notes, or special instructions.
Verify plan sets and engineering
Check that the crew followed the stamped engineering or approved D&E scope of work.
Review workmanship and NEC compliance
Grounding and bonding
Breaker sizing and labeling
Conductor sizing and termination
Panelboard configuration and torque quality
Clearances and accessibility
Confirm system commissioning (when applicable)
For electrical scopes performed after PV installation, verify full system commissioning and monitoring functionality.
Definition: Reducing the main breaker size to achieve required busbar backfeed compliance per NEC 705.12.
Audit Requirements:
Verify the main breaker is derated to the value shown on the approved plans.
Confirm breaker is listed for the panel and is installed in the proper position.
Ensure labeling has been updated accordingly.
Confirm torque quality and that the panel cover fits properly.
Some AHJs (especially flood-zone areas) require electrical equipment to be elevated above a specified height.
Audit Requirements:
Confirm the platform height complies with AHJ requirements (typically based on FEMA Flood Zone Base Flood Elevation).
Ensure the platform dimensions allow for:
NEC 110.26 workspace clearance:
30" width,
36" depth working area,
6.5 ft minimum headroom.
Check structural stability and anchoring.
Most areas will require that it be install on some type of concrete slab. Check highline for guidance.
Ground mounts have to be done to engineering plans and that training of what to look for can be found here.
Audit Requirements:
Verify installation of two ground rods (if required by AHJ)
NEC minimum: 8 ft rods driven full length
Minimum 6 ft separation between rods
Confirm:
#6 AWG copper grounding electrode conductor (unless engineering specifies otherwise)
Correct clamps (UL listed, irreversible crimps where required)
Bonding to the existing grounding electrode system
Ensure rods are flush with or below grade level unless AHJ requires an access point.
Often performed by a licensed contractor or in-house electrician.
Audit Requirements:
Review the scope of work provided to contractor/electrician.
Verify:
Proper grounding & bonding
Correct neutral/ground configuration
Correct wire sizing and terminations
Breaker positions & labeling
Load-side or supply-side connection matches the plans
Workspace clearance (NEC 110.26)
If upgrade occurred before PV install:
Ensure the panel is fully operational and ready for interconnection.
If upgrade occurred after PV install:
Confirm PV system is fully commissioned and monitoring is functional.
Audit Requirements:
Confirm compliance with engineering spec:
Sistered lumber size
Minimum required overlap length
Nail pattern (spacing, stagger, edge distance)
Fastener type (Typically 10D nails)
Verify that the engineer-specified reinforcement pattern was applied correctly.
A more depth training can be found here.
Treated similarly to an MSP upgrade, but with additional neutral/ground separation rules.
Audit Requirements:
Verify:
Grounds and neutrals separated on isolated bars
Subpanel neutral bar is floating (not bonded to enclosure)
Correct OCPD feeder sizing
Conduit installation
Breaker labeling
Workspace clearance
Confirm commissioning if PV was done after initial install.
Audit Requirements:
Confirm depth meets or exceeds NEC requirements:
18" minimum for direct burial (UF-B or USE-2)
24" typical for conduit with individual conductors
Check AHJ/utility rules—some require 24–36"
Verify:
Correct conduit type (Schedule 40/80) (Check plans)
Caution tape placed at required depth (this one is hit or miss really depends on the AHJ enforcement, I wouldn't necessarily fail them for this alone)
No sharp bends or crushed sections
Audit Requirements:
Similar to a electrical install audit and MSP upgrade/sub panel
Ensure that we have completed the requested SOW
And follow the MSP upgrade/Sub panel audit requirements
Audit Requirements:
Confirm what is being requested is complete (very simple)
For all SpS audits, auditors must upload the following:
Clear photos of completed work
Photos verifying code compliance and workmanship
Updated plans annotated as needed
Screenshots of monitoring (if applicable)
Notes summarizing:
Whether the scope was completed
Any discrepancies found
Pass/fail result
Notes for follow-up or re-dispatch
Mark an SpS audit as FAIL if:
Scope of work was not completed
Work does not match engineering or plans
NEC/code violations are present
Monitoring is incomplete or system will not pass inspection
Safety hazards exist
Escalate to Field Support Manager or Electrical Supervisor when:
AHJ requirements conflict with engineering
Grounding or bonding deficiencies cannot be verified
Contractor workmanship is substantially below standard
Structural modifications deviate from stamped engineering