G1 The school maintains accommodation, grounds, facilities, services and equipment to enable it to fulfil its mission.
G2 The technology infrastructure and data systems support the school's teaching, learning and managerial needs.
G3 Auxiliary services as required to support mission and the education programmes offered.
April 2021
Goal 22 - This project is completed and fully compliant.
Goal 25 - The Information Technology Plan 2021 / 2022 and associated new goals will be updated in June 2021.
Goal 26 - An Edureg and InVentry trial is taking place at the RAN Primary School campus this month, towards a decision and implementation over the summer.
March 2021
Project comments were added by the Principals Team (Principals, Assistant Principal, Head of School, Learning Continuum Director) at their 8/4/2021 meeting.
Goal 22 - The Design team has reviewed the placement of the equipment in the Design labs and these are now compliant with the necessary safety standards.
Goal 25 - The Information Technology Plan has been completed.
Goal 26 - InVentry continues to be used at COR and BEE for staff, students and visitors. In May, EduReg (a system currently in place for opening doors only) will be trialled at the primary school for staff in/out access and visitors to see if this system is a feasible alternative or complement to InVentry.
January 2021
Project comments were added by the Principals Team (Principals, Assistant Principal, Head of School, Learning Continuum Director) at their 4/2/2021 meeting.
Goal 22 - The Secondary Principal and the Head of Design are scheduled to meet to once again discuss current safety regulations and the care of shared equipment.
Goal 25 - The Technology Plan is now moving towards the 2021 - 2022 budget completion and significant projects and resourcing for 2021 - 2022 have been identified.
Goal 26 - In January, 'student movement data' was reviewed with a view to examine implications as regards our emergency procedures.
December 2020
Goal 25 - The Technology Plan has been presented to the ISP Board of Trustees and Board Facilities Committees for feedback.
Goal 26 - Testing is underway to examine the possibility of adding automatic electronic gate entrance (staff, students, parents, visitors) to our third and final ISP campus (the primary school at rue de Ranelagh).
IMPORTANT
November - Due to additional expectations with COVID-19 protocols / Lockdown 2 and Home / Online Learning requirements some strategic projects have now been 'paused'.
Note - This area (Domain G) has not been changed in any manner.
October 2020
Goal 25 - The IT Director has been invited to share the IT Plan with the Board Facilities Committee in November.
Goal 26 - SLT is now reviewing and looking at the needs (and options available) for the Ranelagh campus upgrade.
September 2020
Goal 22 - Design workshop safety has been reviewed with changes established.
Goal 25 - A specific IT Action Plan is written annually and published on this Dashboard.
Goal 26 - Risk assessments have been updated and strengthened to include movement between campuses.