Creating a schedule in easy 6 steps
- WBS, WBS Dictionary, Activity Sequencing,
[Assigning Resources, Figure out duration]
(these two can be flipped),
Schedule Reconciliation
Quiz 2 - email - singhsaolcom@gmail.com - email by 4:42 pm.
1. Describe the role of a program manager (4 major functions)?
2. Can a process influence project or product? If so, how?
3. What is the way in Chapter 2 (Project Def and Approach), to
draw a clear rectangle around what would be done in a project?
4. How can you ensure that deliverables are collaboratively delivered?
On to reviewing the org charts -
Milestone - never assign a resource to it
never assign duration to it
Milestone is an outcome of a group of tasks that are assigned to resources.
Duration of each task rolls up to the duration of a milestone.
Trial Project venture with MS Project - Making Pizza :)
Planning -
Milestones and Tasks
WBS Dictionary ??
Predecessors
Assign Resources
Duration
Schedule Reconciliation