Contract Auto-Pay Settings

Learning > Record Pages > Contract (Pay Item) Auto Pay Settings

Background

This record will allow the addition of settings that will control the automated generation of quantities for identified Pay Items in accordance with CDOT specifications. Typically, these settings will apply to what is considered "Auto-Pay" Construction Contract Pay Items such as Mobilization, Traffic Control, or any other applicable Pay Items. This allows consistent and uniform control when automatically generating quantities for Auto-Pay Construction Pay Items while also offering flexibility to adjust the settings for automatically generated quantities if CDOT specifications or requirements change in the future.

PMWeb Access: Navigation Bar > Costs > Contract Pay Items Auto-Pay Settings

Available Reports: None


Job Aids


Record Guidance

The Auto-Pay Settings record is unique to each Project and controls the settings for the automated payments of each specified Pay Item on Pay Estimates. Each line on the form defines the settings for the Pay Item identified in the first column. The form may be viewed by any user, but only edited by System Administrators and Finals Administrators.

Up to five payment "Releases" are automatically calculated and set on any given Pay Estimate when the corresponding "Constraints" are met (i.e. the Release 1 payment occurs when Constraint 1 is met). Two fields define the Release and two fields define the Constraint.

The following provides context for the columns in the Pay Release Parameters table:

Release # Limit Pct: contains the percentage to be multiplied by the Release # Basis value which determines the payment for the Release

Release # Basis: determines the basis to be used for calculating the corresponding Release payment amount. This field has three options:

Release # Constraint Pct: contains the percentage to be multiplied by the Release # Constraint to test if the Constraint has been met. The Release # Constraint field is the reference value to be multiplied by the Release # Constraint Pct to test if the Constraint has been met. This field has four options:

Examples

Example 1

If 5% (Release Constraint Pct) of a $1M Contract Value (Release Constraint = Original Contract Amount less Mobilization & Force Account) has been achieved in total across all Pay Estimates (a total earned Pay Estimate amount of $50K for the totality of all non-Mobilization Pay Items), then 25% (Release Limit Pct) of a $100K Pay Item (Release Basis), or $25K, will be paid.

Example 2

If more than 0% (Release Constraint Pct) of a Pay Item's Pay Item Quantity of 100 (Release Constraint = ORIGINAL Bid Quantity) is included on a Pay Estimate (i.e., any quantities > 0), then 50% (Release Limit Pct) of the Pay Item's Accepted Amount of 40 (Release Basis = all accepted quantities across all approved Daily Diaries), or a quantity of 20 multiplied by the Unit Price, will be paid.

Important Notes


Report Guidance

There are no reports associated with this record.


Workflow Guidance

There is no workflow associated with this record.


FAQs

There are currently no FAQs.