How to Handle Changes During Construction
WHEN TO ISSUE DRAWINGS WITH RFI RESPONSE:
1. To help clarify a field issue
2. If the change is minor and has no cost impact.
3. During Submittal review
WHEN TO ISSUE DRAWINGS WITH A PCD:
1. In the event of Consultant error
2. If there are major changes due to customer request/design improvement/ delays, VECP, unforeseen conditions, acceleration cost, time extension, other with cost implications.
Routing for AFC:
Project Coordinator
Public Works Manager
Facilities Director
Basic Steps to Processing PCD
PCDs are issued after the award of a contract, for the purpose of clarification and / or changes to the work indicated in the original drawings, and which may be made part of the contract through a Change Order. PM should be kept aware when any revisions need to be made to the drawings.
Refer to GRCC, Appendix E (pages 50-51) for requirements.
Step 1: Receive PCD docs and cost estimate from the consultant for review. Have the consultant make any necessary revisions if needed, before processing the PCD.
Any revisions to drawings should be documented by either a delta (if issued as an RFI) or a delta with PCD # (if being issued as a PCD).
In the text of the RFI response, if attaching drawings, indicate the revised drawing sheets and/or detail references.
In the title block of the drawings being revised, indicate the Submittal #, RFI #, or the PCD # in which the change was generated from.
In the title block, indicate the sheet number in reference to the total sheet count.
Cloud only what pertains to the RFI/PCD being issued. Deltas from previous PCDs should remain.
Narrative should include the schedule of sheets being revised.
Date in the title block should match the date on the PCD narrative or RFI.
Step 2: Prep and send AFC No. A, B, C....etc. form and first drawing sheet to the Facilities Director (FD) for approval signatures.
(If the first sheet is a new Title sheet, have the FD sign on the Approval line and in the Revision block). AFC Form
If the PCD is in 8.5x11 format, send AFC and PCD together for approval signature.
Send the drawing sheet and AFC for e-signature as separate emails. Attention your request to May/Marj to be routed for the Facilities Director’s signature.
Step 3: Sequence the AFCs using alphabets, A, B, C, etc. This is to avoid confusion with the Construction Management Section (CMS) AFCs that use numbers.
AFC can be labeled as follows: (AFC A for PCD No. 1, AFC B for PCD No. 2, etc.)
Checklist for AFC:
AFC, FDB Form 53
Consultant Cost Estimate
Form 17 or CPT Job Report
PCD Narrative and Drawings
Step 4: After documents have been signed, submit a print request to May/Marj to order the appropriate number of hard copies.
Verify with CMS or DAGS neighbor islands and the Consultant how many copies are needed.
Oahu:
Have printed copies returned to the PC. PC should package the PCD docs,
AFC and send it to CMS with a transmittal.
Instruct ARC (printing company) to deliver requested copies to the consultant’s office.
Return originals to the PC.
Maui and Hawaii:
Have ARC deliver hard copies to the DAGS office, attention to the Construction Manager (CM) for the job. Verify how many sets are needed.
Email a copy of the approved AFC to the DAGS CM.
Have ARC deliver requested copies to the consultant.
Return originals to the PC.
Kauai:
Deliver to SSFM CM. Verity how many sets are needed.
Email a copy of the approved AFC to the CM.
Have ARC deliver requested copies to the consultant.
Return originals to the PC.
Example of what’s been provided to the Oahu CM:
5 sets of Plans full size
2 sets of Plans half size
7 copies of the PCD Specs (narrative)
1 Cost estimate
2 CDs (CD should include the PCD and all previous bid docs)
*Have a CD made for the files and a half size set of drawings made for yourself if needed.
Step 5: If possible, email an advanced copy of the PCD to CM or DAGS for issuance to the contractor to start working on their pricing.
Step 6: CM will compare contractor’s price against designer’s cost estimate.
If the price is acceptable and the rest of the documents are in order, CM will process the Change Order Proposal (COP) provided funds are available.
If additional funds are needed, CM will request for additional funds via NIF.
Sample Revision Block and Delta: