2023-03-15

Start up the machine as usual.

Plan of Action

It is expected to take 4 hours to break the vacuum, fix whatever is wrong with the FAB, make the seals, turn on the first-stage of pumps then turn on the turbo pumps. It will then take about an evening for the turbo-pumps to bring the vacuum back down to usable levels. If we break the vacuum now, we will make no measurements today, but there is enough time to fix the FAB in the afternoon and still have the vacuum back by tomorrow morning.

For this reason we have decided to try and take some data with TORA in the morning. We will continue the experiment with TORA if results look OK, but if not, we will open the vacuum in the afternoon and fix the FAB.

Mid-Day Update

We can't see any peak at Tora, and because we do not have much time to do more, we change the vertical scale of the scope to 2mV/div range to try to see a signal. The noise level at Tora is much weaker compare to the FAB concerning the RF.

The 2mV/div does not allow us to see the signal. 

We break the vacuum at 12:15pm.

FAB Maintenance

The connections from the feedthrough went: Feedthrough > RG58-like-cable > BNC-gender-adaptor > Short RG-58-like-cable > inner conductor connected to FAB. 

Maintenance

After the vacuum was broken and the blanking flange at the FAB removed, we noticed several problems with the FAB:

To resolve these issues we:

Before restarting the vacuum pumps, we used a multimeter to verify continuity from the feedthrough to the FAB and isolation between the FAB and the vacuum chamber.

Capacitance Measurements

Before the vacuum was re-established, the capacitance of the FAB was measured with the LCR meter. The meter was set to slow measurement without averaging with a 100 kHz signal.

Before the blank flange was connected, this was performed by connecting the kelvin clips to the FAB and to the vacuum chamber directly. The reference measurement (just the leads) gave 0.5 pF and the measurement with the fab gave 228.5 pF, giving a capacitance of 228 pF. 

Since this measurement would not be possible after the blank flange was connected, we verified that the same result was obtained via a coaxial cable at the feedthrough. With the coaxial cable disconnected from the feedthrough the measured capacitance was 307 pF and with the coaxial cable connected to the feedthrough it was 534 pF, giving a FAB capacitance of 227 pF. With this difference, the measurements are considered consistent. 

The coaxial cable measurement was repeated after the blank flange was connected. With the cable disconnected from the feedthrough, the capacitance was 300 pF and with the cable connected to the feedthrough the capacitance was 523 pF, giving a FAB capacitance of 223 pF. Adding the blank flange would be expected to increase the capacitance, so it's surprising that the measurement has reduced, however the change is still small, so could still be attributed to different positions of the kelvin clips or moving of the FAB cable whilst installing the flange. 


Pumping Down

After the vacuum seals were remade, the vacuum started to pump down as expected. The turbomolecular pumps were activated and now we cannot take any more data until the vacuum is back to an operational level. 

Delay 47ms above ^^^

Delay 77ms above ^^^