Swansea Main Drainage Scheme 1931-6

Header: Bracelet Sewage Works 1935

Revealing the scheme, constructed in the tunnels and channels under Mumbles Hill and Includes a reference to the 1997-8 scheme at Knab Rock and of the new Swansea Bay Wastewater Treatment Works.

Headline from South Wales Evening Post, 30th July 1936,  Swansea Reference Library 

On 30th July 1936 in Mumbles, Alderman Edward Harris, Chairman of Swansea's Sewerage and Drainage Committee, officially opened with a golden key "the largest enterprise in the history of the Corporation . . . a marvel of engineering . . ." (South Wales Evening Post) The Swansea Main Drainage Scheme had been built at an estimated cost of £1.8m. At the ceremony the Mayor of Swansea explained to the 1000 guests the background to this " gigantic feat of engineering , , , " that had dominated the Mumbles skyline and coast for 5 years. (Reproduced from Oystermouth Historical Association Leaflet 7,  'Down The Drain')

The Main Trunk Sewer:

Swansea's original sewers were laid down in the 1850s and 60s with additional work carried out in 1895. The system, which discharged directly into the River Tawe and Swansea Bay, was inadequate for the 20th century. With the extension of Swansea's borough boundaries in 1918 to include Oystermouth, Brynau, Cockett, Llansamlet and parts of Penderry and Clase (many parts of which were unsewered) a drainage scheme for the whole, enlarged Borough was essential. Plans were drawn up for a huge project, to be known as the Main Drainage Scheme.

WORK ON THE GREAT SEWER

A Comprehensive Programme of Works:

The solution to the sewerage and drainage problems of the enlarged Borough was to construct some 40 miles of district (subsidiary) sewers which would then drain into a new Main Trunk (Intercepting) Sewer running over 11 miles from Clydach down to Mumbles Head. Here the sewage would be stored in four huge tanks inside Mumbles Hill before being discharged via an outfall into the current of the Bristol Channel 220 yards east of Mumbles Lighthouse. (OHA Archive 'Down The Drain' ).  

Swansea Main Dranage Scheme Key Plan

From Clydach to Brynmill - Contract No. 9

From Brynmill to Mumbles Head  - Contract No. 8 

Key Plan

All the plans are reproduced in a larger format -  Larger photos & plans file >


The full details are revealed -: The Opening  of Swansea Main Drainage Scheme >

The End of Pollution:

At the official opening Alderman Harris declared that although "it had cost a huge sum" the scheme had not only relieved unemployment but also the pollution of the River Tawe and Swansea Bay which had existed for over 100 years would cease." The Evening Post was rather cynical: "The employment has disappeared, the wages spent, but the debt remains and the unemployed. Moreover, the latter were never at best more than a fraction of the army available. As a consolation we have the sanitation of Swansea secured for all time."

However, nothing could alter the fact that the scheme was an amazing feat of engineering and tribute should be paid to those who designed and worked (in often unenviable conditions) upon the construction of the Swansea Main Drainage Scheme in the 1930s. (OHA Archive 'Down The Drain' ). 

The Attendant's House

Earlier

Later

Its operator lived in the building.

This Mumbles bungalow, pictured soon after being built in the mid 1930s, had a secret in the cellar. Built into the cliff face, it housed the village's sewage pumping station, which used to contain the holding tanks, used for the collection of all the sewage for Swansea. When the tide was ebbing, the sewage was pumped out so that the tide could wash it down the channel. 

A Sectional view of the Attendant's House
over the screening chamber
 
By J.R.Heath. M.Inst.M. &.Cy.E. Chief Engineer.
Swansea Main Drainage Scheme, March 1936
Attendant's House over the screening chamber

Screening Chamber, under the bungalow

Over the week following the opening of the scheme, the general public and schoolchildren were allowed to walk through the tunnels.
W.G. Archives, holds a film which records that on teh day of the opening ceromony, The Mayor of Swansea and his entorage, entered the scheme via the Bungalow, built above the Screening Room and from there they were able to walk down into one of four Storage Tunnels (see later photo) each nearly 2,000 feet long, to the Penstock Chamber. The party then climbed a temporary staircase into the Control Chamber (photo) and were then able to exit along the access tunnel, to the Bracelet Bay entrance, near 'The Big Apple.' where refreshments were served.  

The site of the Attendants House, viewed from Knab Rock car park.
Google Maps Streetview, Dec 2023.

MUMBLES SEWER WORKS
More Complaints of Labour Being Imported

MEN FROM OUTSIDE AREA EMPLOYED

IMPORTED LABOUR RESTRICTION

Unemployment Grant from the Government: 

Because of high unemployment in the late 1920s the Government were the 19zys offering grants to local authorities for public utility schemes which would provide employment. Therefore, in 1931, Swansea's Main Drainage Scheme was approved for a Government grant of 63%. Over 1000 men were employed on the main sewer construction, nearly all of them local. But in 1932, 15 miners from Cumberland were recruited (with their specific skills) to construct the tunnels in Mumbles Hill and there were many complaints reported in the local press about labour being imported from outside the area.  (OHA Archive 'Down The Drain' ).  

Storage Tanks

A general view of Mumbles Hill, under which the storage tanks are being constructed

Drilling at face preparatory to blasting 

Concrete and brickwork lining under construction 

"Tunnels stretching into infinity":

The tunnels in Mumbles Hill were blasted out of dense limestone, so that at their deepest point they lay over 200 feet below the surface of the hill. A central ventilation shaft was dug first and then each section of the 4 tunnels was worked upon so that 8 stretches of tunnel were constructed simultaneously. Approximately 75,000 cubic yards of rock were excavated from the tunnels. The work was arduous and not without dangers. Two workmen were killed in 1932 and buildings in Southend were damaged by falling blasted rocks.   (OHA Archive 'Down The Drain' ).  

View of inlet end of one Storage Tank

Access tunnel, photo: Jeff Stewart 

Access tunnels under construction.

Access tunnels under construction.

'Dodson Gang. Mumbles Sewer'. Photo: MA Clare from Mel Clare,. 'Photo: 9.'

Jefery Grace commented, 'My father Albert Ace, is in the white shirt' and Pauline Williams  added -'That's my dad Harry waters in front with shovel.'

One of the vehicles used by construction workers, 1935
'Mumbles Sewer'. Photo:  MA Clare from Mel Clare. 'Photo: 10.'

The Crain on the road.  Mumbles Sewer, 1935. 'Photo: 8.'

Mumbles Head, with Verdi's Itialian Coffee Bar in the forground looking towards Mumbles Pier and Lighthouse.

Pier Cutting Access Tunnels

Few people realise what lies behind the doors protecting the Tunnels at Mumbles Head
Entrance to the 'Fan Chamber,' near the Pier Road Cutting, May 2022

Workmen at the tunnel entrance, 1935.  Photo: M.A. Clare, OHA Archive

Entrance to the 'Fan Chamber,' near the Pier Cutting, May 2022

THE TUNNELS WERE USED DURING WORLD WAR TWO

At the outbreak of war in 1939, the tunnels took on another role when the Brangwyn Panels from the Guildhall, all the best porcelain and glass from The Glyn Vivian Art Gallery, as well as other precious items from Swansea Museum (formerly The Royal Institution of South Wales) were removed to a place of safety, using several of the sewage scheme access tunnels and other locations. Thomas Knibbs, the caretaker of the Glyn Vivian Art Gallery, said that he would check these tunnels every week and in all that time nothing was ever damaged.

"It was very clean inside!"

After the official opening and before sewage use began the works were open to the general public for one week. Visitors to the 4 storage tanks inside Mumbles Hill walked into the tanks and saw some of the 10 million bricks used in the sewer construction. "I think the bricks were white and it was very clean," recalls one Mumbles resident from her visit as a child. The Evening Post described the tanks (each 1995 feet long, 16 feet wide and over 10 feet high and lined with bricks) as "stretching into infinity ... electric lights twinkling smaller and smaller into the distance ..."    (OHA Archive 'Down The Drain' ).  

Bracelet Bay 

During routine maintenance, it was possible to have a glimpse into the access tunnel for the 'Penstock Chambers Control Room' situated on the eastern side of Bracelet Bay. 

Control room over Penstock Chambers 

Sheila Davies comented on Facebook - 'The sewage works was through a large green door in the side of the the cliff, as a nurse tutor I had to take student nurses on a visit to see how the sewage was dealt with before being discharged some distance out at sea.'

The Mumbles Outfall, Bracelet Bay,  March 2022

When completed the doors were wooden and smart, but now the entrance is looking a little battered.

The Mumbles Outfall, Bracelet Bay,  around 14 May 2023

This Facebook post reported that the doors are open and damaged, as well as this had been reported the the Water Company. 

The Mumbles Outfall, Bracelet Bay,  March 2022

Soon following the report, the doors had been repaired.

Bracelet Bay and Mumbles Lighthouse:
The entrance door to the Drainage Scheme can just be seen, c.1955

Before

Mumbles Pier and Bracelet Bay, after the opening of the new cutting and road to Limeslade.
The upper path, in the centre, leads to the Refreshement Rooms at the beach.
The car park will not be constructed on the common until after 1936. 

Before

Bracelet Bay and Mumbles Lighthouse, c.1900. 
The car park will not be constructed on the common until after 1936. 

Bracelet Bay Before and After

Before 

Bracelet Bay  possibly pre 1914, donated by Mary Lewis.

Before 

This pre 1920s photo shows Bracelet Common, which stretched from the beach, over Mumbles Hill,  is seen before the 'Drainage' scheme created the car-park.

By 1936, large quantities of stone had been mined to creat the various tunnels for the scheme. Most was used to create the popular Bracelet Bay car park (seen below) and  some stone infilled the old Iron Mine cutting  on the Hill, from above Knab Rock.

After

Photo: March 2012

After

Photo: April 2010

Work in progress

'Part of the Sewerage Works, Mumbles'. Bracelet Bay, 1935'.  Photo: M.A. Clare
A colourised version of the photo, from Ronald Studden 

Disruption at Bracelet Bay and Mumbles Head:

A series of photographs taken in 1935 by M.A. Clare illustrate just how Bracelet Bay had become unrecognisable. The Evening Post described it as "one huge silver grey spoil bank of excavated limestone, down which shutes run and over which electric lights glitter. ... It is possible to see 50 yards or so down one of the tunnels, and, when it is aglow with electric lamps, it is [like] Aladdin's Cave, from whose inky depths comes the pulsating of a hidden engine."

 (OHA Archive 'Down The Drain'

Bracelet Bay Sewage Works , 1935.

A distant view of the crane off the Lighthouse, during the laying of the sewage pipes, c.1935.

Undoubtedly, the most hazardous part of the entire scheme was the provision of the outfall east of the Mumbles Lighthouse. Contemporary photographs show an aerial ropeway carrying material out to an otherwise inaccessible site. 

A powerful crane, transported by barge was used to help lay the pipes in an open trench and tunnel across the Inner and Outer Sounds of Mumbles Head. Work was constrained by tide times and delayed by bad weather, but successfully completed.   (OHA Archive 'Down The Drain' ).  

The twin sea outfall pipes at Mumbles Head, 1936

Sea Outfall - Cast Iron Pipes in Trench

Sea Outfall under construction with crane at Mumbles Head, c.1935 -

The top of  the Sea Outfall and supports for the crane (shown in the earlier photo) along with the remains of the WW2 causeway, at Mumbles Middle Island , April 2012

These railway lines were photographed by Barbara Parry, during a walk to Mumbles Lighthouse, near the crane shown in the earlier photo.  It is not sure if they had a connection to this scheme., or the construction of the causeway built in WW2. 

Sea Outfall under construction at Mumbles Head, c.1935 (and below) -

Sea Outfall under construction, Mumbles Head, c.1935

Additional research by Jack Hartley


The sea outfall was the most hazardous section of the scheme. An engineer with experience of this work, Mr. J. P. Pike, was appointed to supervise its construction. A tunnel was excavated from the foot of Mumbles Inner Head to the outlet chamber for twin 5 feet diameter cast iron pipes. It measured 14 feet by 7 feet 6 inches and cut to 11 feet below the surface of the foreshore. The cutting was continued for 765 yards across the rocky shore at an average depth of 9 feet 3 inches to the outlet bay, about 220 yards due east of Mumbles Lighthouse. The pipes were laid side. by side and surrounded by concrete. Much of the work was carried out in a concrete cofferdam. Tidal and weather conditions caused delays, available working time towards the seaward end was limited to a few days during each range of spring tides.

In October 1935, a diver was employed to inspect the results of blasting a channel in the solid rock of the seabed. Mr. J. H. Foster of Port Talbot was paid £7 per week when diving and a retaining fee of 35 shillings per week when not. A diving outfit was hired from Messrs, Caffin and Co., Ltd. The total fall from the end of the storage tanks to the outfall bay is 15 feet, the end of the pipes are just submerged at low water of ordinary spring tides. This completed the Main Trunk Sewer.

Sea Outfall under construction with shuttering and crane at Mumbles Head, c.1935 -

Mumbles Lighthouse - Later

Mumbles Lighthouse, taken from out to sea at low tide, which reveals the top of the sewer pipe, as well as the pillars on which run the railway lines for the crane memtioned earlier.  Photo: Ronald Studden. 

Additional research by Jack Hartley


The visitors were taken on a conducted tour of the workings. 

The report in the South Wales Evening Post was vivid:

"The visitors were conducted behind the bungalow. There, under the wire screen which catches debris which escapes occasionally down the steep cutting into the tall hill, they had their first glimpse of the immense proportions of the work. From there until they emerged upward into daylight through the access tunnel into the Bracelet cliff, and on to promenade roadways created by the use of debris from the excavations in the hill, they were surrounded by brickwork or concrete.

Everything was cleaned for the occasion, and stewards, police, stairways and barricades prevented any deviation from the route chosen. Lights will remain, till the time comes for the scheme to operate, along the roofs of the storage tanks, and in the case of the one traversed precautions were taken against the remote possibility of a failure in lighting. First the visitors passed down steps to the screen house, rounded its machinery, and then walked along the large access tunnel running into the hill. A stairs took them into the storage tanks. They arrived in No.3 of the four. A floodlight placed here showed only a little distance along this immense tunnel of brickwork, its lines of specially hard bricks beautifully finished. Then they crossed into No. 2 - there are 20 feet of solid material between each - and passed along its whole length of almost 2,000 feet. To say that each tank has a capacity of nearly two million gallons does not convey much to the average person, but the length is hinted at when it is stated that apparently the eye sees the overhead lights to only about half the length, that is where the access from the Cutting road reaches the tanks. And the tanks are so wide that on each side of the deeper central channel four people walk abreast easily. Here and there along the side were noticed the controlled escapes for the many pockets of water, characteristic of limestone, met with in the hill. These escapes close as the tanks begin to fill.

At the end of the tank the guests lowered their heads to pass underneath a steel penstock through which the tank is to be emptied, across a tunnel and up stairs to the control room of the penstock chamber, where Alderman Edward Harris operated one of the main penstocks to open tanks to the sea. Guests then proceeded to the Pier where tea was served."

In the same edition a long article by Mr. J. R. Heath described the early attempts at drainage, the pre-1918 expansions and planning, the sewering of the town and the construction of the Main Trunk Sewer. He paid tribute to his predecessor, Mr. H. H. Wyrill, to Alderman Edward Harris, vice chairman Alderman Daniel Evans, and the Committee members, to the contractors, and to the Ministry of Health's chief engineer and his staff for their help and advice. Finally, "and by no means least", to the unemployed men who performed the manual work, many of them adapting themselves to arduous, difficult and unaccustomed work. "The results speak volumes for their tenacity, especially as many of them began with the great handicap of having been without work for long periods. After only brief training they adjusted themselves to what was often specialist work and have done work, the quality of which could not be excelled in this country."

The public were invited to inspect the work during the following week. Then subsidiary sewers were connected to the Main Trunk Sewer in stages beginning at Southend and ending at Clydach, gradually bringing the system into operation.

Early Plans of the Scheme

When the idea of an outfall at Mumbles Head was considered in 1911 it was necessary to prove that currents and tides would take the effluent away from land out into the open sea. This was done by series of float trials. A floating object was placed in the water at the proposed site of the outfall, followed in a sea-going motor boat with a crew of two, and a surveyor or pilot plotting the course by sextant readings of prominent buildings or features on the shore. This procedure was repeated at each hour of a daily tide cycle and on several days so that every stage of the monthly tide cycle had been tested. 

The results were plotted on 12 large scale charts. Such tests at Swansea Pier in 1894, 1896 and 1911 showed it an -unsuitable outlet. 101 tests from a point just east of Mumbles Lighthouse from 26 August to 8 October, 1911 showed that effluent discharged from 3 hours before to 5 hours after High Water would be carried down channel and away from the land.

High Water to 1st Hour after High Water I Hour's Ebb.
Float suitable for Tidal Observations 

The outlet would have to be closed for four hours of each tide during which sewage would continue to flow and would need to be stored. Only by creating space within Mumbles Hill could this be done.

Plan showing intended sewerage dated 1924.

Additional research by Jack Hartley

''Pack up your plant at once and you can go''

Adaptation of Rudyard Kipling's poem "If read in a speech at the commemoration dinner for the opening of the Main Drainage Scheme by Mr R.A. Whitson of Messrs Melville, Dundas & Whitsun, contractors for the Brynmill Mumbles section of the works. It refers to the difficulties in boring through the solid limestone of Mumbles Hill. (South Wales Evening Post, 1st August 1936)

If you can keep your head when all about you, 

Are fissures, caverns, caves and water too, 

When Mumbles rock is all around about you 

And when it's falling down, you don't quite know 

How concrete by the tone with satisfy the problem, 

And set the bricks by millions in a row -

Well, never mind, you still get on with it,

And push the job to see the sewage flow.

So, at long last, the whole darned scheme is finished. 

The Chief is pleased and did say so.

"The work is good that you have finished,

So pack up your plant at once and you can go."

Sectional Views - Sea Outfall at Mumbles Head 

(Click here for larger photos >)

Sea Outfall
Control room over Penstock Chambers 
Attendant's House 

Sea Outfall - One

Sea Outfall

Sea Outfall - Two

Access Gallery

Sea Outfall - Three 

Elevation of Attendant's House 

Plan - One

Sea Outfall

Plan- Two

Plan- Three 

Blackpill Through Time 

A special feature of this length is the syphoning of the Main Trunk Sewer underneath the Clyne River diversion (near Blackpill Station), Here the syphon takes the form of three 3ft. diameter cast iron pipes dipping below the new concrete culverts carrying the diverted Clyne River, with a large brick chamber containing penstocks at either end.

It was necessary to carry the sewer under the embankment of the L.M.S. Railway at Blackpill, and the use of cast iron tubing was resorted to for the tunnelling process at this point.

The embankment of the L.M.S. Railway at Blackpill, 

The Mumbles Train at Blackpill Station 

The Mumbles Bay Rider at The Junction Cafe

The Sewage Pumping Station at Knab Rock 

Pictured around 1997, this new scheme planned to pump the sewage back to Fabian Way, so that it could be treated at the Swansea Bay Wastewater Treatment Works. After treatment, this would be released into the bay through a new outfall.

This scheme would greatly improve the water quality off local beaches as it would replace the need to release untreated sewage through the outfall off Mumbles Lighthouse. 

Swansea Waste Water Treatment Works

Swansea Bay Wastewater Treatment Works was built in 1998 at a cost of £40 million. The majority of the sewage treated at the works came from the Swansea Valley and eastern and central areas of the city, and had the capacity to deal with waste received from 188,000 households. 

 Acknowledgments 

The research and assistance is greatly appreciated from: 

Main Drainage Works, a booklet, published by the County Borough of Swansea upon the opening of the scheme, on Thursday 30th July 1936.

Oystermouth Historical Association Archive, Leaflet 7,  'Down The Drain'.

South Wales Evening Post, 1930-36

SWANSEA - Dŵr Cymru Welsh Water.  

 Swansea Reference Library; 

Kate Jones 2003 and 2007;

William Welham;

The Family of M.A. Clare; R.H. Clare;  

Carol Powell; 

David Spooner

Betty Sivertsen 

and Stuart Bishop. 

More: The Opening  of Swansea Main Drainage Scheme >
Includes full details of the scheme up until the opening, including  Contracts and Contractors. 

More: Larger photos & plans file >