Revit
MUB Assembly
Gantt Chart
groupmates had little to no history with software
Had to redo the first floor due to issues
difficulty with files loading, and installation on computers
difficulty bringing autocad files into Revit
Different coordinate systems for each floor
boundary lines to edit floos and roofs.
Original first floor scaleing caused us to rebuild entire floor
Firstly tasks were in order of all floors' beams, floors then walls. This required us to remake the Gantt chart in order of floor, beams, exterior walls, interior walls, and then the roof.
Required to remake Gantt chart
Future Plans
Through each Revit modeled floor, MUB assembly, renovations, facility management report, master program and construction simulation, we learned how to problem solve, analyze, and use teamwork in the engineering profession to achieve the completion. Secondly, gaining knowledge throughout the class, lab and an outside environment allowed us to intake information in the engineering and surveying profession that we otherwise would have not attained. Lastly, by using Revit, Microsoft Project and NavisWorks, we learned how to use our knowledge and skills with BIM to complete the Memorial Union Building. With all of the learning outcomes achieved, we plan on taking all knowledge and information with us in the future. Learning BIM is vital for experience leading into the industry. Problem-solving and teamwork will translate with us in every aspect of life between class, jobs and the industry. With everything said, each part of this project will translate and help us conquer greater achievements in the construction industry in the future.
Project Timeline/Schedule
January 22nd: Start of the design of individual floor models in Revit.
February 19th: Start of Interim Report.
February 26th: Start of Interim Project Presentation.
February 23rd: Deadline of the design of individual floor models in Revit.
February 23rd: Start of MUB Assembly Model.
March 7th: Deadline for Interim Project Presentation.
March 7th: Deadline for MUB Assembly Model.
March 15th: Deadline for completion of Interim Report.
March 18th: Start preparing for the Master Program (Microsoft Project).
March 20th: Start Final Report.
March 31rst: Deadline for Master Program (Microsoft Project).
April 1rst: Start Construction Simulation (Autodesk Navisworks).
April 1rst: Start research on Property & Facility Management in BIM.
April 7th: Deadline for Construction Simulation (Autodesk Navisworks).
April 7th: Start of Project Website.
April 10th: Deadline for report on Property & Facility Management in BIM.
April 19th: Deadline for Project Website.
April 19th: Deadline for Final Report
Gantt Chart