Next Meeting: TBD
Project Overview
Kenilworth is a DC Public School swing space located in Ward 7. This project aims to improve the swing space in support of DCPS' ongoing modernization efforts across the District. This will be accomplished through an approximately 6700 SF multipurpose, and kitchen addition. After the addition is complete, the bubble will be demolished to allow additional space for outdoor education and recreation facilities. Kenilworth will support Thomas Elementary School during School Year 2024-25 as construction is ongoing.
Project Details
Location: 1300 44th St. NE
Ward: 7
DCPS POC: Mars Eagleson
DGS Project Managers: Sonali Ambre
Design-Build (DB) Team: Studio MB and Bennett Group
Start Date: Fall 2021
Project Completion: October 2025
Status: Construction Phase
Eastland Gardens Civic Association Construction Update and Letter of Support Meeting - 4/15/2025
Topics Covered: Construction Update/Letter of Support
ANC7D Presentation for a Letter of Support Request - 4/8/2025
Topics Covered: Project Overview/ Engagement/Design & Construction Overview/Letter of Support
Eastland Gardens Civic Association Survey Results and Construction Update Meeting - 3/18/2025
Topics Covered: Construction Update/Letter of Support
Thomas-Kenilworth Community Meeting - 2/26/2025
Topics Covered: Design Presentation/Construction Overview/Letter of Support
Eastland Gardens Civic Association DOB Permit Follow up Meeting - 2/18/2025
Topics Covered: Design Presentation/Construction Update/Letter of Support
Site Walkthrough - 2/14/2025
Topics Covered: Project Scope
Eastland Gardens Civic Association DOB Permit Meeting - 1/21/2025
Topics Covered: Status Update/Letter of Support
Eastland Gardens Civic Association Meeting - 11/19/2024
Topics Covered: Project Overview/Site Conditions/Abatement Work/Upcoming Construction
Community Kick-off - 1/17/2023
Topics Covered: Project introduction/Swing Space Overview/Open Dialogue