Bard Early College HS
Next SIT Meeting: TBA
Project Overview
The facility at 1351 Alabama Avenue is being redesigned and modernized to become the new home of Bard High School Early College DC, a district-wide high school program whose students work towards both a high school diploma and an Associates Degree. The four-story building is undergoing changes to move from an open-plan elementary school to a 21st Century high school facility. Phase II of the project will also provide significant improvements to the site.
Project Details
Project Location: 1351 Alabama Ave SE (new location)
Ward: 8
Start Date: School Year 2020-21 (Design)
Completion Date: Phase I: December 2022, Phase II August 2023
DGS PM: Tom Henderson, Jahdal McKenzie
Design-Build Team: MCN Build, Perkins Eastman DC
Project Status: Year 2 Construction
DCPS Contact: Diana Halbstein
Education Specification (EdSpec): Bard HS Early College EdSpec
Project Resources
Project Updates
Project Update - September 23, 2022
Project Update - July 29, 2022
Project Update - April 14, 2022
Project Update - April 1, 2022
Project Update - March 18, 2022
Project Update - March 4, 2022
Project Update - February 22, 2022
Project Update - February 4, 2022
Project Update - December 23, 2021
Project Update - December 10, 2021
Project Update - November 5, 2021
Project Update - October 1, 2021
Project Update - June 25, 2021
Meeting Materials
SIT Meeting 2/16/2022
Community Meeting 10/27/2021
SIT Meeting 10/13/2021
Construction Kickoff Meeting
SIT Meeting 3/16/2021
SIT Meeting 3/11/2021
SIT Meeting - 1/12/2021
SIT Meeting - 1/7/2021
Community Meeting - 12/9/2021
SIT Meeting - 12/2/2020
Community Kickoff Meeting - 6/23/20