Whitlock ES (Former Aiton) 

Next Meeting: To be Determine

Project Overview

Aiton Elementary will receive a complete modernization to meet DCPS’ educational specifications.  The modernized Aiton Elementary building will be roughly 73,000 square feet.  The modernized building will address the Americans with Disabilities Act (ADA) and code requirements. Learning, instruction, and support technology will be brought up to capacity and cutting-edge standards.   


Classrooms with appropriate square footage will be created from the original floor plan concept to create an adequate 21st-century learning environment and meet the DCPS educational specification standards. The new modernized design will integrate discovery commons spaces, small group rooms, and resource rooms to accommodate special projects, collaborative work, and individual pull-out instruction. The modernized design will allow for robust physical education and dining services. 


The modernized facility will serve approximately 271 students. As part of the design process, the design team will work closely with the school leadership, various DCPS Central Office departments, the Aiton Elementary School-specific School Improvement Team (SIT), and the broader community to better understand the community vision and the unique Aiton Elementary School culture. 


Project Details

Education Specification (EdSpec): Whitlock EdSpec 

Project Resources

Project Updates


Meeting Materials:


Whitlock Interior Design Update SIT Meeting, Wednesday, November 15, 2023


Back-to-School SIT Lorraine H. Whitlock School Wednesday, September 13, 2023


End-of-Year SIT Wednesday, June 7, 2023


Eastland Gardens Civic Association Q&A January 17, 2023

Design Development Back-to-school SIT 

Schematic Design Feedback SIT - August 16, 2022

Schematic Design SIT August 09, 2022

Concept Design Feedback SIT - May 02, 2022

Concept Design SIT - April 27, 2022

SIT Meeting - March 31, 2022

Kickoff Meeting - June 08, 2021