Coolidge High School Addition
Next Meeting: TBD
Project Overview
Coolidge High School is a DC Public School located in Ward 4. An approximately 5,000 SF addition will accommodate the relocation of the music wing to provide space for Coolidge High School’s own cafeteria and kitchen. The project is designed with a focus on sustainability through the incorporation of LEED for School - Gold design principles. The addition is tentatively scheduled for completion in Summer 2025 to support the school in School Year 2025-26.
Project Details
Location: 6315 5th St. NW
Ward: 4
DCPS Project Manager: Mars Eagleson
DGS Project Managers: Sonali Ambre/Kerric Baird/Cassidy Mullen
Design-Build (DB) Team: Bennett Group DC and ISTUDIO Architects
Start Date: January 2023
Project Completion: August 2024
Status: Construction Phase