Burroughs Elementary School is a DC Public School located in the Brookland neighborhood of Ward 5. The project is a 75,000 square-foot modernization that will upgrade the building's systems and technology while meeting the District's sustainability goals through the achievement of LEED Gold and Net Zero certifications. The project also calls for the construction of a modular swing space campus, on the Burroughs field, containing approximately forty classrooms, a large multi-purpose space, a modular kitchen, two playgrounds, and covered, ADA-compliant access. The modernized Burroughs Elementary School will re-open its doors to students, staff and the Burroughs community in Summer 2027 for School Year 2027-28.
Project Details
Location: 1820 Monroe St. NE
Ward: 5
DCPS POC: Melissa Pegram
DGS Project Manager: Patrick Moloney
Design-Build (DB) Team: Gilbane and Quinn Evans and WKM Solutions
Start Date: Summer 2024
Project Completion: Modular Campus: Summer 2025 / Modernization: Summer 2027
Status: Construction Phase ( Modernization)
Project Resources
Construction Updates
Modular Campus
Modernization
Meeting Materials
Back To School Community Meeting - 9/29/25
Topics Covered: Project Overview/Design Updates /Construction Updates/ Open Discussion/ Next Steps
Design Development & Interior Concept SIT Meeting - 6/5/25
Topics Covered: Project Overview/Design Development Drawings/Interior Concept Plans/ Open Discussion/ Next Steps
Exteriors and Playground Visioning PT.2 SIT Meeting - 5/15/25
Topics Covered: Project Overview/Construction Timeline/Overview of Site Plan/ Survey Results/ Concept Designs/ Open Discussion
Community Meeting - 4/30/2025
Topics Covered: Project Overview/ Modular Campus Construction Timeline/Modular Campus Updates/Feedback from Community Members
SIT Schematic Feedback Meeting - 2/4/2025
Topics Covered: Project Overview/ Schematic Design Recap/Feedback from SIT Members
SIT Schematic Design Meeting - 1/28/2025
Topics Covered: Project Overview/ Schematic Design Introduction/ Clarifying Questions
Community Meeting - 1/16/2025
Topics Covered: Project Overview/ Modular Campus Construction Timeline/Modular Campus Site Logistics Plan/Feedback from Community Members
Exteriors and Playground Visioning SIT Meeting - 12/10/2024
Topics Covered: Project Overview/Construction Timeline/Overview of Site Plan/ Design Team`s Vision for the Playground/Feedback from SIT Members
ANC 5B Monthly Meeting - 11/20/2024
Topics Covered: Burroughs Modular Campus Construction Update/ Design Updates/Questions
Join Online : https://dc-gov.zoom.us/j/84897308816?pwd=UTlFUndzVFZiQ1NLVFVYNG1RVmIvZz09
Meeting ID: 848 9730 8816
Passcode: 956733
Join by Phone: 1-301-715-8592
Meeting ID: 848 9730 8816
Passcode: 956733
SIT Concept Feedback Meeting - 9/18/2024
Topics Covered: Project Overview/Construction Timeline/ Concept Design Recap/Feedback from SIT Members
SIT Concept Meeting - 9/12/2024
Topics Covered: Project Overview/Construction Timeline/ Concept Design Introduction
SIT Kick-off - 6/12/2024
Topics Covered: Project Overview/Design-Build Team Introduction/Construction Timeline and Logistics Plan
Community Kick-off - 5/28/2024
Topics Covered: Project Overview/Design-Build Team Introduction/Construction Timeline and Logistics Plan
Recording and transcript
Councilmember Parker Community Meeting on Swing Space Decision - 1/23/2024
Presentation (not presented; no AV available)