Project Overview
Coolidge High School is a DC Public School located in Ward 4. An approximately 5,000 SF addition will accommodate the relocation of the music department to provide space for Coolidge High School’s own cafeteria and kitchen. Although subject to change, the classroom addition is tentatively scheduled for completion in Summer 2025 to support the school in School Year 2025-26. The Cafeteria/Kitchen renovation is anticipated to be complete in Winter 2025.
Project Details
Location: 6315 5th St. NW
Ward: 4
DCPS POC: Filip Nelson
DGS Project Managers: Sonali Ambre
Design-Build (DB) Team: Bennett Group DC and ISTUDIO Architects
Start Date: January 2023
Project Completion: December 2025
Status: Construction Phase