Building Refurbishment

July Update

14-07-2020

Our new innovation hub is also progressing with the classroom stripped, plastered and awaiting paint and flooring next.

14-07-2020

Phase one of our rebuilding and renovation work is nearing completion the new entrance is almost ready and will have the finishing touches added over the summer holiday.

May Update

06-05-2020

Phase one of our rebuilding and renovation work is nearing completion as the new entrance is block is fully glazed, and all of the interior is fitted out.

We're just waiting on the finishing touches and then we'll get the building ready for a grand reveal when we're ready to open again.

April Update

03-04-2020

The glazing is going in and the exterior is almost complete. We can't wait to see the cladding going on in the coming days.

February Update

03-02-2020

The roof is now on and being made watertight and the rear walls are being finished ready for the windows and doors to be added in the coming weeks.

January Update

20-01-2020

We've had our first look inside the new building and we're amazed with the size of the new entrance hall and offices. The rooms are taking shape now and within the next few weeks the building's outer cladding and glazing should be completed.

16-01-2020

The timber frame of the building is almost complete. Our builders have worked incredibly hard this week to get most of the buildings framework completed this week.

07-01-2020

The new entrance and office foundations are almost ready for the concrete to be poured.

December Update

10-12-2019

Our builders are working hard despite the awful weather! The first foundations for our new conference room have been poured today.

09-12-2019

The walls of the new meeting rooms and offices are starting to appear as the first bricks are laid.

03-12-2019

The walls are starting to appear as the first bricks are laid.

November Update

30-11-2019

The concrete foundations have been poured and the building sites has been cleared ready for the walls to be constructed.

15-11-2019

The pillars have come down and the digger has cleared the site and dug out the foundations ready for our new building to be constructed.

October Update

21-10-2019

The site has been almost completely cleared of the old link corridor with only the brick columns left standing.

08-10-2019

Work has begun this month to demolish the existing link corridor and remove the trees from around the building site on Hurstcroft Road.

Building Work:

We’re excited to announce that over the next 12 months our main building will undergo a major facelift & refurbishment with the demolition of the current link corridor & caretakers house & the construction of a smart new entrance on the Hurstcroft Road side of our building.

Hurstcroft Road Elevation - New Admin Block Main Entrance and Corridor

New Link Corridor Admin Block Playground Elevation

Associated Plans and Documents

Updated February 2020