How to pull 2.5" Pre-connect



HOW TO PULL 2 ½” 150’ PRE CONNECT



1. Take position

a. On tailboard

b. Captain’s side

2. Access rear pre connect

a. Release cover straps

b. Fold cover up

3. Access nozzle bale

a. With left hand

4. Right hand under nozzle bale

a. Pull load out

i. 2 – 3 feet

b. Step off rear tail board

5. Maintain neatness of shouldered load

a. Right hand under nozzle

b. Left hand on top of shoulder stack

6. Pull shouldered load

a. Onto shoulder

i. Turning counter clock wise

ii. Right hand transitions to top of stack load

b. Clear remaining shoulder stack load from bed

7. Grasp pull loop with left hand

a. Pull remaining hose

i. Advance towards objective

1. Drop hose when bed has cleared

8. Continue to advance hose

a. Allow hose to pay off top

b. Manage hose

c. To arrive at objective