FY2014 Facility and Diagnostic Milestones
F(14-1): Complete installation and testing of refurbished D-Site Rectifier Firing Generators
The refurbished D-site rectifier firing generators will be installed and tested to support integrated systems testing of the D-site FCPC power systems.
D(14-1): Complete the Multi-Pulse Thomson Scattering (MPTS) diagnostic in-vessel hardware modifications
To support post upgrade operation, the MPTS diagnostic in-vessel hardware modifications will be completed to be ready for a system test and calibration of the diagnostic.