ELECTRICAL SERVICES - CODE VIOLATIONS
Sector 2
ELECTRICAL SERVICES - CODE VIOLATIONS
Sector 2
The intention of the code language surrounding working clearance for electrical equipment has to do with safety and maintenance:
Electrical equipment can very quickly become a fire hazard when you consider all the types of code violations or damage that can be sustained over time if not maintained.
In the event of a fire, this equipment needs to be accessible to fire response personnel and anyone in the home who may be responding to an electrical fire first.
Electrical equipment needs to be accessible for maintainance purposes:
Electrical meters need to always be accessible by the utility.
For general maintenance of breakers and disconnects, clutter and vegetation needs to be cleared around this area.
There needs to be space for the door of any electrical enclosure to be able to open at a minimum 90 degree angle.
All electrical equipment must have sufficient clearances as described in NEC 110.26.
The simplest way to think of this is to imagine a phone booth around the equipment:
There should be NO obstructions within 36" in front of the equipment
The equipment needs to fit in a clear window on the wall measuring a minimum of 30" by 6'6".
Note that under NEC 110.26.(A)(3) Exception 2, existing systems may be grandfathered in if the working clearance height is less than 6'6", however, all new equipment will be required to comply to the full 6'6" height clearance.
The most important factor is the working depth. There shouldn't be anything obstructing within 3' in front of the electrical equipment. The height (6'6") and width (30") requirements are a window with the electrical equipment permitted to be located anywhere within this window.
It is important to screen for working clearance violations with existing equipment but we also need to ensure that the new PV electrical equipment will be installable with adequate working clearance as well.
Service Wire Insulation (TAPS ONLY)
If your inteconnection method is going to be a supply side or load side tap, you must ensure that there is a proper amount of insulation around the serivce wires you will be working on.
If the wire is not insulated all the way to the lug, then a TDR is required, otherwise, it will likely arc when electricians are applying piercing connectors in and pressing down on the dead front.
Example pictures:
First photo shows the site survey image the design was based on. Second photo shows the arcing and damage that occurred at install when the field tech applied pressure to the connecting wires when tapping.
Working clearance around gas meters are usually dictated by the utility. We will follow the general rules that most utilities follow as seen on the right:
a clear 3' radius around the regulator will be required.
A clear 3' zone vertically above the meter is required up to 10'
All areas outside of these clear zones are permitted for us to mount our equipment. The new equipment ALWAYS needs to comply with the clearance requirements listed above.
Existing services that come into the default working clearance of gas meters will be grandfathered in with the utility, so there will be no need to flag this unless utility requirements explicitly say so.
give extra attention around A/C and other mechanical units, debris, shelving and other obstructions. These objects should not be obstructing the needed working clearance:
Do not plan to mount equipment directly behind a mechanical unit.
Look for viable areas on either side of these mechanical units.
If the existing service is fully obstructed by a mechanical unit or other permanent obstruction, Flag for PER Escalation.
For a window to be considered a point of egress, it will need to meet the following criteria:
The window is operable, meaning it can be manually opened or closed.
The open side of the window must be at least 2' wide.
We are mainly concerned about egress windows on the first level or whichever level is on grade with the electrical equipment.
DO NOT PLAN TO MOUNT BELOW ANY POINT OF EGRESS.
Electrical equipment should never be mounted directly over stairs. This is most often seen on decks and flood platforms.
You may install over an even grade like a deck or flood platform, however, you should never install electrical equipment over or under a stairway associated with such platforms.
If you see any permanent violation of working clearance, Flag for PER Escalation.
Indoor electrical panels should never be located:
In bathrooms
In a closet
These circumstances will result in an ESC 100% of the time and will require PER Escalation
Meters should never be located in an enclosed space behind a door with a locking mechanism:
All meters must be fully accessible by the utility.
For Site Survey:
Document and clearly notate any indoor enclosed meters in Field Pro
For Design & Engineering:
Flag for PER Escalation if you see this.
Gates and fences can sometimes be a similar issue. If the gate has a lock on it, the utility could require that you relocate the existing meter to be accessible. Most of the time, however, this will be grandfathered in. However, this will add special considerations for the new PV wall equipment.
In this photo, the fence is barely visible in the photo. You need to determine if the equipment is behind or in front of this fence on the property early on in the planning process.
This photo shows very clearly that the existing equipment is behind the fence.
This means we need to plan for where the new equipment will go. For most utilities, you need to plan for new AC disconnects and PV meters to be located in front of the fence but as close to the existing equipment as possible.
This can vary depending on utility. For example, CORE has said to put the new equipment with the old behind the fence before in the past.
Designers need to check the utility requirements closely
Surveyors need to get photos on either side of the fence in this situation.
This is the final planned layout that was submitted to the utility.
We will get into utility required PV equipment later in the design training.
Should we be concerned about the obstructions in front of the equipment on the left?
NO. The clutter in front of the electrical equipment is not permanent and it would be reasonable to ask the customer to move these items.
The rule of thumb here is if obstructions would take more than 30 minutes or so to move, an Electrtircal Review will be needed.
Another very common clearance issue is overgrowth in front of existing electrical equipment.
But in a case like this, should we move "A" & "B", just "A", or just "B"
It's easy to get tripped up on a situation like this, but the fact of the mater is, the existing equipment will be perfectly within working clearance if we simply remove "A"
We can even likely fit some or all of the new PV equipment directly to the right of the meter and still have 30" of space for the meter and new equipment to occupy making it perfectly within working clearance.
The Designer would need to create a homeowner obligation to remove the vegetation in front of the existing equipment.
Looking closely, what are some issues you can spot in this image?
There are two potential issues here:
The AC unit is encroaching in the 36" depth clearance required directly in front of the meter.
The meter is mounted quite high and is likely over 6'6" above grade. This can be an issue with some utilities.
PER Escalation should be completed in this case.
Looking closely, what are some issues you can spot in this image?
There's really only one issue:
The space between the fence and the meter/main appears to be about 2'
The required working depth in front of electrical equipment is 3'
This should be flagged for PER Escalation
Looking closely, what are some issues you can spot in this image?
There are two issues here:
The working space "window" around the panel is required to be not less than 30" though the equipment can appear anywhere in that window, it does not need to be centered in it.
In this specific case, there are obstructions inside of the needed 30" window, no matter where it is measured from.
There is a work bench obstructing the required working depth. It is unclear if this work bench is permanent or relatively movable.
This should be submitted for Electrical Review
Looking closely, what are some issues you can spot in this image?
It looks like there might be a sufficient 30" window of clearance that the equipment is mounted in, however, there is one issue that needs to be fixed:
There is permanent shelving and other temporary items blocking the needed working depth clearance.
This shelving is the main concern. It appears that it would most likely take more than 30 minutes to relocate.
These items are also obstructing the needed clearance, but they can simply be shifted over 3' to the left to provide ample clearance.
This would take less than 30 minutes.
This shelving may or may not be an issue. From this visual alone, it looks like it could be 30" away from the left edge of the panel, but we would need precise measurements to be sure.
So what should the designer do?
The designer should submit this to Electrical Review due to the permanent shelving obstructing the working depth. Additional notes can be added about shelving that may also be coming close to the working clearance.
Looking closely, what are some issues you can spot in this image?
In this example, we have both an AC unit and a gas meter grouped with the meter. So what are the considerations here?
The AC unit is fine as is. It appears to be well over 3' away from the meter providing sufficient clearance.
However,
The meter is mounted too close to the gas diaphragm on the gas meter.
We will need to ensure that there is a mounting area nearby where we can mount the new wall equipment without encroaching on the default clearance around the gas meter.
This example is a little more tricky. There is no doubt there are objects obstructing the required working depth. There's two main questions to ask to figure out if Electrical Review will be required or not.
Do the obstructions appear to be permanent?
Things like piping, gas meters, sinks, etc. would be considered permanent.
Things like shelving, fridges and other appliances can sometimes be moved as a customer obligation.
How long would it take to remove the obstruction(s)
If it is just clutter, it should always be a customer obligation.
With shelving and appliances, if it looks like it would take more than about 30 minutes to correct, it should be flagged for PER Escalation
In this case, it is just clutter and the shelving does not appear to be bolted to the wall. This should be called out as a Customer Obligation.
In this example, we have bushes in front of the meter obstructiong working depth clearance in front of the existing equipment.
This should be called out as a Customer Obligation.
The 2020 edition of the NEC introduced some new requirements regarding service disconnects. Not all jurisdictions using the 2020/2023 will require us to upgrade older services but some of them might, so it is important to know the updated code specifics regarding services.
Below are the new articles and updates from the 2020 text.
(2020 NEC) 230.85 Emergency Disconnects:
For one- and two-family dwelling units, all service conductors shall terminate in disconnecting means having a short-circuit current rating equal to or greater than the available fault current, installed in a readily accessible outdoor location. If more than one disconnect is provided, they shall be grouped.
2017 NEC and prior:
There was previously no requirement for there to be an accessible emergency disconnecting means outdoors. In many older markets such as Virginia, Oregon, South Carolina, etc., you will often see "stand alone" meters, meaning that the main disconnect/MSP is indoors somewhere which was allowed in older versions of the code and may be allowed to be grandfathered in depending on the jurisdiction.
The principle difference is that the 2020 NEC requires an outdoor accessible emergency service disconnect.
(2020 NEC) 230.71(B) Maximum Number of Disconnects:
Two to Six Service Disconnecting Means. Two to six service disconnects shall be permitted for each service permitted by 230.2 or for each set of service-entrance conductors permitted by 230.40, Exception No. 1, 3, 4, or 5. The two to six service disconnecting means shall be permitted to consist of a combination of any of the following:
(1) Separate enclosures with a main service disconnecting means in each enclosure
(2) Panelboards with a main service disconnecting means in each panelboard enclosure
(3) Switchboard(s) where there is only one service disconnect in each separate vertical section where there are barriers separating each vertical section
(4) Service disconnects in switchgear or metering centers where each disconnect is located in a separate compartment
Essentially, this is saying, we may have up to 6 service disconnects. Service disconnects are main disconnects that are located between a power source (utility, PV, Customer owned generator, etc.) and loads being serviced by this source (typical branch circuits like lights, laundry, appliances, etc. that are attached to load side branch breakers.)
2017 NEC and prior:
A residence was still only allowed up to 6 service disconnects, however, it used to be allowed to have all 6 service disconnects in a single enclosure.
The principle difference is that the 2020 NEC requires each service disconnect to be in a separate enclosure with only one main service disconnect per enclosure.
230.67 Surge Protection:
(A) Surge-Protective Device. All services supplying dwelling units shall be provided with a surge-protective device (SPD).
(B) Location. The SPD shall be an integral part of the service equipment or shall be located immediately adjacent thereto.
Exception: The SPD shall not be required to be located in the service equipment as required in (B) if located at each next level distribution equipment downstream toward the load.
(C) Type. The SPD shall be a Type 1 or Type 2 SPD.
(D) Replacement. Where service equipment is replaced, all of the requirements of this section shall apply.
2017 NEC and prior: This is another service requirement that did not exist prior to the 2020 NEC.
The principle difference is that the 2020 NEC requires each service to be equipped with an SPD.
Regardless of code cycle, you we always need to comply with the 6 handle rule. Let's review the code specifics. This is the 2017 verbiage:
230.71 Maximum Number of Disconnects:
(A) General. The service disconnecting means for each service permitted by 230.2, or for each set of service-entrance conductors permitted by 230.40, Exception No. 1, 3, 4, or 5, shall consist of not more than six switches or sets of circuit breakers, or a combination of not more than six switches and sets of circuit breakers, mounted in a single enclosure, in a group of separate enclosures, or in or on a switchboard or in switchgear. There shall be not more than six sets of disconnects per service grouped in any one location.
In the image to the right, you'll see a split bus panel. The highlighted blue breaker positions represent spaces meant to house service disconnects. The red section is meant to house light loads. The lower bus is supplied by service disconnect "2." notice that there are actually 10 handles in the upper bus position meant for service disconnects.
This is a violation of the 6 handle rule. The designer should plan to consolidate some of these breakers on the lower bus if possible. If not, it will need to be flagged for PER Escalation.
There are two basic types of MSPs you will commonly see with no main breaker:
Main lugs panel (pictured left):
The main lugs of this panel feed the entire bus.
All breakers on the bus can be de-energized independently from each other.
Split bus panel (pictured right):
The main lugs feed only the breakers on the upper bus
One of the breakers in the upper bus position is feeding the lower bus. This breaker is the “main breaker” for the lower bus.
So how would we count 6 handles?
On a main lugs panel:
Count every breaker on the bus below the main lugs.
It should not exceed 6 handles. If it does, double check the labeling to see if the bus diagram indicates a split bus configuration.
On split bus panels:
You only need to count the number of breakers on the upper bus connected to the main lugs.
Give special attention to the bus diagram to determine which spaces are on the supply side bus.
For Site Survey:
Document and clearly notate any violations of the 6 handle rule and make clear notes in Field Pro.
For Design & Engineering:
Flag for PER Escalation if you see more than 6 handled disconnects on an MSP with no main breaker.
Strictly following the most recent 2020 edition of the NEC, the existing service needs to have:
A single main disconnect per enclosure (no 6 handle rule)
An exterior disconnect beside the meter
A surge protective device.
Some areas using the 2020 NEC will allow us to grandfather in old service equipment such as:
Split bus panels with 6 handles or less on the supply side
Interior main disconnect/no exterior main disconnect
No surge protection.
Others will enforce the full extent of the 2020 NEC when interconnecting solar. Check this section of the tool for guidance.
Some utilities or AHJs may require residential load calculations to validate that the existing main breaker is sufficient to feed the loads:
Make sure to double check the utility and AHJ requirements for this for each project
This is also required if we need to derate the main breaker for any reason regardless of AHJ/Utility requirements
Flag for PER Escalation if calculations fail.
Occasionally, you may see a typical plug-in type branch breaker acting as a main breaker for a load center. This is called a backfed main breaker. There are some additional rules to be aware of for this tpe of set up:
408.36 Overcurrent Protection:
In addition to the requirement of 408.30, a panelboard shall be protected by an overcurrent protective device having a rating not greater than that of the panelboard. This overcurrent protective device shall be located within or at any point on the supply side of the panelboard.
(D) Back-Fed Devices
Plug-in-type overcurrent protection devices or plug-in type main lug assemblies that are backfed and used to terminate field-installed ungrounded supply conductors shall be secured in place by an additional fastener that requires other than a pull to release the device from the mounting means on the panel.
Essentially, when a plug in type breaker is used as a main service disconnect, we need to ensure that there is a mechanical hold down, also called a retaining kit, that is attaching the breaker to the enclosure. Note this does not apply to main disconnects on the load side of the main service disconnect such as a sub panel main breaker.
EATON BR
For BR type breakers, this will usually be a retaining screw.
Note that it is considered a code violation and/or equipment damage for holes to be drilled in other types of breakers to suit a retaining screw.
This should mainly be seen on BR type breakers with some older discontinued brands such as Challenger or Westinghouse
CUTLER-HAMMER
For CH type breakers, you will often see either a white or red tab indicating the mechanical retaining attachment.
SIEMENS
For Siemens type breakers, you will often see either a white or red tab indicating the mechanical retaining attachment.
This is more subtle because some times it may be a small gray clip as seen in the photo on the right.
SQUARE D HOM
There are a few different types of retaining kits used with HOM type breakers. Most often it is some type of metal bracket.
make sure you can see the attachment to the enclosure.
SQUARE D QO
There are a few different types of retaining kits used with QO type breakers as well. Most often it is some type of metal bracket or a plastic bracket as seen to the right.
make sure you can see the attachment to the enclosure.
What is double lugging?
More than one wire landing on a single lug on a branch breaker, main breaker or main lugs.
When is it allowed?
Only when the breaker labeling indicates that it is allowed.
Some square D breakers allow this:
2 copper wires are allowed to land on one lug
2 aluminum wires are not allowed
1 copper & 1 aluminum is also not allowed
If you see double lugging, explore the following solutions:
Look to see if the bus has space to land additional breakers to separate circuits as needed.
Look to see if you can tandem any breakers to relocate one of the circuits.
The example to the right demonstrates that double, or even triple lugging as in this example, can be subtle at a first glance.
Notice if you look closely, you can see that there are actually two conductors in each of the main lugs.
Notice there is also a set of additional mechanical lugs attached to the main lugs. These also have conductors in them.
Even though the additional lugs don't look as suspicious, they are still a form of double lugging.
This should be flagged for PER Escalation.
This example has is slightly less subtle, though it is not highlighted so that you can practice looking for it.
The breaker with the sticker reading "Lts" has two wires landing in it.
One of these conductors needs to be relocated to a new breaker. If that is not an option, it needs to be flagged for PER Escalation.
Review:
What is a tandem breaker?
1 space, (2) 1-pole 120 circuits.
What is a triplex breaker?
2 space, (1) 2-pole 240 circuit + (2) 1-pole 120 circuits
What is a quad breaker?
2 space, (2) 2-pole 240 circuit
How do we know if a bus accepts tandems?
Panel labeling
Serial Number
Notched Stabs
Every space on this bus accepts tandems according to the labelling.
If you see illegal tandems, explore the following solutions:
Move from a space that doesn’t allow tandems to one that does if this is an option.
Look to see if there is space on the bus or unused breakers to relocate loads onto
The bottom 10 spaces on this bus would accept tandems according to this label.
For Site Survey:
Document and clearly notate this type of code violation in Field Pro
For Design & Engineering:
Flag for PER Escalation if none of the above options work.
Refers to breakers that are installed such that when the breaker is in the “on” position, the handle faces down.
This needs to be corrected prior to installation.
There are several breakers in this example that are upside down.
One of the service disconnects is upside down.
Three breakers on the lower bus are upside down.
The most common sighting of this violation will occur with the main breaker on older load centers.
Flag for PER Escalation if you see this.
Panel labels will help us determine the following:
Existing breakers are compatible with the manufacturer
Bus/Main breaker rating is sufficient for solar
Typical wiring diagram:
Determining if the panel will allow tandems
Determine if panel is split bus
It is critical that we get a photo of any and all labeling for existing electrical equipment.
Labels can also tell us the NEMA rating of the equipment. NEMA rating is an alphanumeric rating system used to designate the weather resistance of an enclosure.
Watch out for NEMA type 1 and 2 equipment outdoors: these are only approved for interior use.
In many cases, you can tell an interior panel from an outdoor panel simply by its appearance.
indoor type load centers have a much smaller and flimsier door cover
Indoor/flush mount panels often have the walls of the box unfinished. This is because it's meant to be imbedded in the house framing on the interior and is not intended to exposure to the elements. Hence the Type 1 rating.
Flush mount refers to a panel that is recessed into the fall such that the deadfront is flush with the walls surface.
It is most common for flush mount load centers to be indoor rated but it is not a hard and fast rule.
You should still check the labeling and look for other context clues to support that it is indeed an indoor rated enclosure.
Surface mount means that the entirety of the enclosure is mounted on the surface of the wall, rather than recessed into it.
It is most common for flush mount load centers to be outdoor rated but it is not a hard and fast rule.
Again, you should still look for multiple pieces of evidence to support this.
Semi-Flush is most often used to refer to outdoor surface mount equipment that is slightly or fully recessed into the wall.
This is common in markets such as New Mexico, Nevada and Colorado.
Most often will hold a type 3 or type 3R NEMA rating for outdoors.
This is an example of an indoor rated panel installed illegally outdoors:
You can see the smaller "indoor" type hinge door
You can also see the unfinished sides of the panel and the cover flaring out. This implies it is meant to be flush mounted indoors
Finally, the label reads as "Type 1 Indoor Enclosure"
Based on this label, can this load center be mounted outdoors?
Yes, a rating of 3 and above designates equipment as resistant to outdoor conditions.
Based on this label, can this load center be mounted outdoors?
No, type 1 & 2 are indoor only.
Based on this label, can this load center be mounted outdoors?
No, this is type 1.
Based on this label, can this load center be mounted outdoors?
No, this is type 1.
For Site Survey:
Document and clearly notate any Indoor type panel being used outdoors in Field Pro.
For Design & Engineering:
Flag for PER Escalationif you see a type 1 or 2 enclosure outdoors.
Often, people misunderstand that ground and neutral serve different purposes and can cause some to use these terms interchangeably.
So, what’s the difference between ground and neutral wires?
Neutral wires are a designated path for active current to return to the main service entrance only.
Ground wires are an intentional low impedance path for stray current (fault current) to safely dispel into the earth.
Electricity follows the path of least resistance, so grounding systems are meant to be very direct and are present throughout the circuitry of the home.
There is also a distinction between MSP wiring and Sub Panel wiring that needs to be noted.
Ground and neutral should never be bonded (connected) in any sub panel enclosure.
This means that sub panels will require both a neutral and a ground wire connecting to the MSP.
It will also mean that grounds and neutrals for each branching circuit need to be on separate terminal bars.
You shouldn't see green/bare wires and white/gray wires on the same terminal bar in ANY sub panel.
The example on the right shows a typical ground bar on a sub panel. Notice, there are only wires that are either bare or with green sheathing on this terminal bar. The visible white wires are terminating on a separate insulated neutral bar not visible in this photo, but present just under the breakers.
When should ground and neutral be bonded?
Only at the main service disconnect.
Ground and neutral are bonded either by landing on the same terminal bar or by forming a connection between ground and neutral bar through other means such as a green screw bonding the insulated neutral bar to the enclosure.
This means that in the MSP You CAN have green/bare wires and white/gray wires on the same terminal bar.
The example on the right shows a fairly common ground/neutral terminal bar as seen in an MSP enclosure. Notice that both bare AND white wires terminate on this bar.
The MSP is typically the termination point for the Grounding Electrode Conductor (GEC) which secures the home structure to the Grounding Electrode system.
This is a system devised to disperse excess current from the electrical system.
This can also be required on panels that are on a completely separate structure such as a separate panel that appears on a garage separate from the main home.
Further clarification is provided in the National Electrtical Code (NEC). The NEC is the international code governing electrical installation standards and safety under the Nation Fire Protection Association (NFPA).
There are 8 items that are listed in NEC 250.52 as allowable grounding electrodes, here is the list:
Metal Underground Water Pipe
Concrete-encased Electrode
Metal In-ground Support Structure
Ground Ring
Rod and Pipe Electrodes
Plate Electrodes
Other Listed Electrodes
Other local underground metal systems or structures
When viewing this image, imagine you are looking at a the neutral bar terminal in a sub panel. What's the problem here?
We have a bare ground landing on the neutral bar.
grounds and neutrals need to be separated in any sub panel enclosure.
If this panel does not already have a designated ground bar that is not bonded to the neutral bar, this ground should be relocated there.
If there is no ground bar whatsoever, we will need to instruct the installer to install a new ground bar terminal and add it to the BOM as a generic part.
This is a perfect example of a sub panel that has proper separation of grounds and neutrals.
It is completely acceptable for ground wires to be double lugged with wires of the same size. The example to the right would not warrant any additional work or corrections of any kind.
While it is acceptable to double land grounds in the same terminal, this is not the case with neutrals
Neutrals should never be double landed like this.
The designer needs to instruct the installer to get these neutrals on their own terminal by either relocated to another terminal lug on the existing neutral bar or by installing a new insulated neutral bar terminal if there are no available spots.
All conduit runs must have secure connections to:
Electrical boxes
Other raceways
Watch out for MC/FMC being used outdoors without a PVC liquid tight jacket:
For Site Survey:
Document and clearly notate any exterior MC/FMC.
For Design & Engineering:
Flag for PER Escalation if you see FMC without PVC jacket.
NM (or Romex as it is commonly referred) is the flat constructed cable, typically consisting of either one or two live wires, one neutral wire, and one ground wire encased in the sheathing of the flat cable. This is the most common type of cable used for residential interior wiring.
NM (Romex) should not be used for exterior wire runs. Additionally, while Romex can be run through conduit in some circumstances, it is not typical and should be reviewed.
Unapproved use of Romex outdoors, unprotected.
For Site Survey:
Document and clearly notate any exterior NM or NM running through conduit.
For Design & Engineering:
Flag for PER Escalation if you see this.
The main thing to be on the lookout for is undersized service conductors and feeders.
These conductors are sized to handle a specific current rating.
Most often, you won't be able to read the wire labeling to determine the size of the wire, so you will need to use your better judgement.
This is an example of undersized wire in a 200A disconnect.
For context, these are aluminum wires which would need to be sized at 4/0 AWG to handle 200A.
The minimum would be 2/0 AWG if the conductors were copper.
Refer to the chart above as a loose guide. These conductors appear to be no larger than 2 AWG Al. This is severely undersized.
Flag for PER if you see this.
This example is the same load center. Look closely to see if you notice any other issues.
This branch breaker is rated for 100A. The rating indicates that it is likely servicing a sub panel elsewhere in the home. These wires look suspicious.
The minimum AL conductor rated for 100A would be 2 AWG.
The conductors plugged into the 50A 2P breaker on the other side of the bus look closer to 2 AWG than the sub panel feeders do.
Flag for PER Escalation if you see this.
This is what typical service conductors and feeders should look like:
Banjo meters are identified by a meter base that is abnormally small, usually only occupying the total size and area of the meter bulb. Also look for:
abnormally small service risers
or
no riser at all, only SE-R cable going to the service drop.
Flag for PER Escalation if you see this in any area outside of Oregon.
This is another example of a Banjo Meter. The problem with these meter sockets is that they indicate that the service is only rated for about 60A which is not suitable for most modern households.
For overhead services, the following clearance rules apply:
Weatherheads coming up through the roof need a minimum 24” clearance above the roof.
Max run over the roof surface is 48”
In residential walking areas, the overhead clearance must be maintained at 10.5’
12’ clearance required over public walkways
18’ clearance required over public streets
If you notice that the service riser does not appear to meet these requirements, Flag for PER Escalation
As we talked about earlier, service wires should never be touching the roof.
Max overhead span over the roof is 48”.
These service cables are spanning completely over the other side of the roof.
This should be flagged for PER Escalation
These service cables are only about 8 inches off of the roof. The minimum clearance over the roof is 18" with the minimum service drop height being 24"
This should be flagged for PER Escalation.