Change Order Rework Options
Proactive Due Diligence
Department Responsible Options
A simple breakdown of which Department Responsible options should be selected in certain situations.
Account Validation/Sales Support
If the utility bill or other required documents have not been uploaded prior to the stage they would be needed.
Compliance
If a previous Change Order called for rework that wasn't needed, didn't call out required rework or didn't address the full change order request details (such as the entire permit rejection as provided in the change order).
If the AHJ or Utility's design requirements either weren't complete (as in we didn't note a requirement during the Due Diligence process, so the designer didn't see it), if requirements or code cycles are incorrect in the Highline Database (either because they updated their code and we didn't catch it or because we marked the wrong ones) or if the wording of the requirement is too vague or incomprehensible.
Customer Experience
If the Customer Experience department
Design
If the plan set, final design, BoM or Installation CD uploaded by the designer shows incorrect information - name or address (check the utility bill), equipment type and amount, system size, or incentives - or is not showing required information - AHJ/Utility-specific notes/equipment/labels, customer incentives, etc.
NOTE: Double check any archived by the engineer or PER to see if they match. Sometimes the engineer or electrical reviewer may accidentally delete certain aspects of the design deliverables which may lead to an error.
If the Design shows something that is not installable according to what's shown in the Site Survey.
If the survey photos don't include photos of something that caused the installers to pull off, but the installers have provided photos, we need to double check if it's something that would be required by Site Survey SOP. If it's something like code violations or damages that isn't made known in the site survey photos, that would fall on Site Survey, not design. If it's a standard thing during the Design Data Collection process that the designer overlooked, it would fall on both.
Design Validation
If the homeowner was not made aware of more large-scale changes to the system such as system size increase/decrease, layout, change of inverter or production changes greater than 5%.
If there was a previously completed change order for financial where there is a later issue with NTP or financial that results in a change order. gets opened
Electrical Review
If the Design deliverables were archived and a new one was uploaded by PER which doesn't match the design, but does cause an error.
If PER calls for a variance when one is not allowed or approved.
If a PER tech specifically calls out an incorrect Scope of Work in an SpS object for ancillary work.
Engineering
If the Design deliverables were archived and a new one was uploaded by engineering which doesn't match the design, but does cause an error.
If the documents for the wrong project were uploaded or the documents are missing.
If the documents don't have stamps on pages that should be stamped.
Field Support
If the Field Support tech prescribes some deviation from the plans and doesn't create a change order which later causes a fail at inspection.
If the Field Support tech provides a "fix" that is a legitimate cause for rejection at inspection.
Highline Development
If the BoM or Special Equipment doesn't show all the needed equipment.
If the Design Tool calls for cables or conduits that are undersized or aren't allowed for their designed use.
HOA
If the homeowner's HOA is incorrectly halting the project for illegitimate reasons, we would select HOA.
Inspections
[Working with department on what would be an attributable error]
Install
If the installers did not follow plan or there was something not called for on the plans that was the cause of a rejection.
Installation Scheduling
[Working with department on what would be an attributable error]
Jurisdiction - AHJ
If the plan reviewer during the permitting stage asks for changes that aren't up to code or fails us for something not found in the adopted codes.
If the inspector fails us for something that is not found in the code or cites incorrect or unapplicable code.
Jurisdiction - Utility
If the utility company rejects for something not listed in their requirements (requires us to do research and update the Highline if legitimate).
Permitting
[Working with department on what would be an attributable error]
Project Coordinator
[Working with department on what would be an attributable error]
Project Funding
[Working with department on what would be an attributable error]
Proposals
[Working with department on what would be an attributable error]
Resolutions
[Working with department on what would be an attributable error]
Sales
[Working with department on what would be an attributable error]
Sales Liaisons
[Working with department on what would be an attributable error]
Site Evaluation
[Working with department on what would be an attributable error]
Site Survey
[Working with department on what would be an attributable error]
Special Services
[Working with department on what would be an attributable error]
Structural Review
[Working with department on what would be an attributable error]
Supply Chain
[Working with department on what would be an attributable error]
Utility
[Working with department on what would be an attributable error]
Special Considerations
In some situations, if the error is due to a single entity, but they followed their SOP for the role or it's attributable to a lack of clarity in the given scenario, it will be assigned to "[Department] SOP" which just means the manager's or director's (in the case of Design) name should be in the Tech Error Override field (if you don't have access to that field, please reach out to someone on the team who does, such as the manager or queue lead). Please note, if it is tech error overridden it will not count as an error against any selection within the Department Responsible section.
If there are multiple departments that didn't follow their SOP which ultimately contributed to the error, each department that failed should be selected.
For example, if Site Survey didn't provide clear photos of the MSP interior and the Designer pushed the project forward without a resurvey, both the Site Survey and Design options should be selected in the Department Responsible since both failed in SOP.
ANY change order that is not supported anywhere in the project (such as if the creator claims we installed IQ7s instead of IQ8s when the design deliverables and install photos all show IQ8s), or is based on incorrect information for that project, needs to have the Change Order creator's department marked as the Department Responsible. This is because it was made in error.
Note
It is our responsibility to understand other departments' SOPs to more clearly determine whether they followed or overlooked something contributing to the error.
Please reference the departmental SOPs and responsibilities here: General Operations Trainings
Change Order Rework Options
A simple breakdown of which rework options should be selected in which situations.
Financial
Any contract or financial changes need to be sent for Financial Rework
Sales
Proposals
Site Survey
Insurance Inspection
Preliminary Structural Review
Preliminary Electrical Review
Design
Engineering
Plan Set
If the authorizing entity (AHJ, utility or homeowner/rep) states that something on the plan set needs to be changed.
If there are aspects of the plan set that would be a code violation.
If the installers deviated from the plan set and the installation photos don't show a code violation and the AHJ/Utility require a resubmission for the associated change.
Design Validation
If there is a change in system size, a layout change causing 10% or more decrease in production or a change in financing due to ancillary work (such as an ESC).
Permit - Solar
Do NOT use! This should be removed.
Permit - Electrical
Do NOT use! This should be removed.
Special Services
If there is ancillary work deemed necessary
Utility - NEM
If the system size is changing, the layout change increases the production estimate or the service equipment is being changed.
If the Utility company requires a resubmission whenever the permit is revised as described in the utility account in Salesforce.
Rebate
Do NOT use! This should be removed.
HOA
If the change order was
Supply Chain
If the warehouse needs to order certain special equipment aside from when creating a service appointment.
Install
If the installers need to return and perform some service, such as gathering missing photos of our installation or change specific aspects of the system.
Inspection
If the inspection has taken place, was rejected and we need to send a response letter.
Utility - PTO
If after the AHJ's inspection, the plan set needs to be revised and the system size is changing, the production estimate is increasing or the service equipment is changing.
Double check the utility account on the Salesforce page for their specific revision notes.
Permitting
If the plan set needs to be revised prior to install.
If the plan set needs to be revised and the AHJ doesn't allow red-lining for the change at install, meaning they require a revision resubmission for the change.
Due Diligence
[TBD]
No Rework Needed
If the change order is simply to note that something has taken place, but the project can proceed as normal.
Example: If the AHJ/Utility does not require as-built revisions, but the installers deviated because the design was inefficient for install. The plan set is fine, but the design process may have been incorrect. Double check if the designer followed SOP.
Proactive Due Diligence
Proactive Due Diligence is the process followed when an error is reported directly from the AHJ or the Utility for something that needs to change on the plan set. Examples of this can come in many forms from code references not up to date to contractor signatures missing that are now required. These issues are often simple but can affect multiple accounts and needs to be addressed before follow up can begin.
SOP Updates
4/1/25 - If you are pushing back on an AHJ/utility for a requirement like a placard or equipment etc. Please when the conversation is finished forward it to the OM of the area.
2/5/25 - When sending for survey or install missing photos for anything in the attic please make sure to include that they need to provide a site map of the location of what they find.
2/4/25 - Refresh the queue each time you grab a CO, check the owner field to verify it only says compliance, and immediately change it to your name (Do not look through it and then put your name on it). This prevents instances where someone claims it and then some minutes later someone else claims it and closes it out.
2/4/25 - When sending for electrical stamps that you are checking the stamp type. If it's digital and structural has already stamped it then electrical can't stamp it. So either design needs to separate the plan set or the unstamped plans need to be unarchived.
1/7/25 - PPAs won't need as plan set revision for the TSRF if that changes do to module relocation or anything like that. DV will just request a Final design revision for those docs which is what light reach will only care about.
1/7/25 - Chicago interconnection: If the main service panel is directly back to back, or on an unfinished exterior wall (i.e. unfinished basement wall) then we will be connecting following the standard interconnection SOP. If that is not the case, we will default to the exterior supply side tap splice box, similar to the CPS supply side tap
8/5/24 Crews can do a panel removal and reinstall the system in one day if we assign it to a crew. We will need a roofer to replace the damaged shingles after we remove the panels as her roof will be damaged in the removal process. The installers will leave the attachments in to maintain the water seal of the roof until a roofer can come replace the shingles. We will need a Home damage SpS record opened for this.
5/21/24 - When completing a change order and need to get a custom placard, tag the Warehouse manager and the OM. You will still need to send to design to have them provide a engraved mapping placard sheet.
Any time a place updates to 2023 NEC or needs new labels, we need to (in addition to updating autocad and/or highline) send an email to Zachary Landers to let him know about the label change and where it applies to. For brand new labels, he'll need a good picture of it and the material, size, and other specs.