SUPPLY SIDE CONNECTIONS
Design
Put simply this would be:
Equipment upstream from (above) the main disconnect breaker.
This equipment will always be energized, whether the main breaker is on or off.
Equipment downstream (below) from the main disconnect breaker
This equipment can be de-energized by switching off the main breaker.
Identify Service Conductors by simply investigating where the main conductors for the load center are coming from:
Conductors from the Meter to the MSP are Service Conductors:
If you change the main breaker to the off position, the Service Conductors will still be energized by the meter.
Sub panel feeders are not Service Conductors:
If you change the main breaker in the MSP into the off position, this also de-energizes any sub panel feeders connected to the MSP.
The Service conductors are highlighted in the photos to the right.
Identify supply side buses by simply investigating how the main bus is being supplied:
Any MSP bus being fed directly through lugs from the meter is considered a supply side bus.
Note that supply side buses need to comply with the 6-handle rule: no more than 6 handled disconnects on a supply side bus.
Sub panels being fed through lugs are not supply side buses. These will need to be fed from a breaker.
In the images below, supply side buses are highlighted green while load side buses are highlighted purple.
Note that when there is a disconnecting means between the bus bars and the service conductors, then the entire bus will be considered load side equipment.
What is backfeed?
Backfeed is a term used to describe the total output from the inverter feeding into the residential loads.
How is it calculated?
NEC 690.9 (B): Backfeed device ratings shall be no less than 125% of the [inverter] maximum continuous output current.
Simple formula:
# of inverters x Max inverter output current x 1.25 = Backfeed needed
Example: 19 module system using IQ8+ inverters
(19) x 1.21 = 22.99A
22.99A x 1.25 = 28.74 A
30A Overcurrent Protection Device (OCPD) Needed
What’s overcurrent protection?
An overcurrent protection device (OCPD) is a device that is meant to protect against overcurrents such as:
Overload
Short circuit
An OCPD rated for the backfeed current is always required for any interconnection type. NEC 705.11(C) Overcurrent Protection
The BASELINE DT. will do this math for you when you input the circuit sizes:
Max of 13 modules per circuit
The OCPD rating in the BASELINE DT. tells you how much solar we are backfeeding into the existing residential system.
So how much PV can you land on the supply side?
You can land up to the rating of the Service for a supply side connection.
Example:
A 200A Service can handle up to 200A of PV on the supply side.
NEC 705.11(A) Output Rating: The sum of the power source continuous current output ratings on a service, other than those controlled in accordance with 705.13, shall not exceed the ampacity of the service conductors.
Here's the basic run down:
A Supply Side Tap can be used when the meter is detached from the MSP.
Supply side taps can never be used on a meter/main combo.
Must have at least 5” of Service Conductor for a typical tap using piercing connectors which is standard here at Ion.
All supply side taps must have an Overcurrent protection device within 10 feet of conductor length from the splice point. Install outdoor fused disconnect if possible, if not then use an indoor load side breaker.
When interconnection is on an exterior panel or on a panel that is back to back with the meter, a fusible disconnect will be used.
Fusible disconnects are an outdoor rated disconnecting means
The thin filament inside the fuse will melt when met with overcurrent and fulfil the same purpose as a breaker. Fuses always need to be replaced when the filament breaks
A standard fuse is pictured to the right.
Next to it, we have fuse reducers.
Reducers are used when the fuses are smaller than the standard size for the disconnect.
Indoor OCPD Load Center AC Disconnect for a supply side tap uses a different piece of equipment:
Instead of a fused disconnect, a breaker type disconnect is used
Why wouldn’t we just run cable from and exterior fusible disconnect to the location of the supply side tap in this case?
NEC 230.72(A): The two to 6 disconnects, if allowed by 230.71, shall be grouped. Each disconnect shall be marked to indicate the load served.
A supply side connection is considered a secondary service (Parallel power production system) as defined by the code and is allowed by NEC 230.71.
Most meter/main combos have factory manufactured Service Conductors or bars between the meter and main disconnect.
Sometimes you might see factory feeders coming from a main disconnect or meter to an interior panel back to back with the outdoor equipment
Identify factory conductors as conductors that are perfectly parallel with each other sharing perfectly machined bends in the conductors at the same points as seen between the meter and main disconnect in the photo on the right..
These types of manufactured conductors cannot be tapped.
This is another example of a meter/main using manufactured conductors that cannot be tapped.
Notice that the feeders attached to the load side of the topmost service disconnect are not manufactured type feeders and could be tapped if needed.
When there is a generator installed on the clients home, we will usually default to a supply side tap.
Why?
PV must be installed in a way to prevent it from interacting with generators.
Supply Side Tap for Automatic Transfer Switch Generator Systems:
When a Generator is in use with an automatic transfer switch (ATS), interconnection needs to default to a supply side tap in the ATS enclosure.
This is another example of generator equipment you might see associated with an ATS type generator system.
The ATS can be a separate enclosure, or it might be included in the body of the generator itself.
If you see this, you will need to figure out where this equipment appears in the residential system wiring and ensure that we interconnect on the supply side of this equipment.
Supply side tap for generator systems:
When a Generator has a manual interlock kit, we need to default to a supply side tap in the MSP. (pictured lower right)
If the manual interlock kit is in a sub panel, a load side breaker may still be used in the MSP.
In most cases you will need to use a supply side tap though.
You should always look at photos of any load center with the deadfront on as this type of equipment can very easily be missed otherwise which can result in a design change at install and you will be liable as the designer.
Some utilities require that the supply side tap occur in a separate junction box.
Special considerations:
Requires a TDR:
A TDR is a request for the utility to cut power to the meter temporarily to make it safe for our installers to cut and splice feeders.
Requires special materials to be added to the case
Here we have an MSP that is indoors. Note that a breaker type interconnection is always preferred over a tap, however, 2 spaces are needed for a PV backfeed breaker. There are also allowable backfeed considerations to think about when making interconnection decisions. Lets take stock of what we know from this image:
The main breaker is 200A
This means that the bus is either also 200A or it may be 225A
This means we can quickly deduce that the max possible allowable backfeed, assuming 225A, is 70A using the 120% rule.
This figure would be reduced to 40A if the bus is ALSO 200A and not 225A.
The other thing we know is that this panel is full of GE slims.
Note that a 1 space 2P GE slim can still be used as a PV breaker but only if positioned between two stabs to allow for a 240V connection.
Now we can check the total system backfeed by simply looking at the system size.
The total backfeed for this system will be 100A
60 * 1.21 * 1.25 = 90.75.
The next nearest OCPD rating up from 90.75 is 100A.
This means we will be well over the backfeed threshold to even consider a load side connection. We know we need to complete a load side connection.
We can complete a supply side connection via supply side tap so long as we do not exceed the ampacity rating of the service conductors. Our service conductors here are rated for 200A, so we will be in the clear with 100A of backfeed.
Here we have an outdoor meter standing alone. This means the MSP must be on the interior of the home. This is where it can be tricky, especially with supply side connections.
Remember that for supply side connections, all service disconnects must be grouped.
When we interconnect on the supply side, the OCPD we are using is considered a service disconnect.
For load side connections, this will not matter.
When we interconnect on the load side, the OCPD we are using would not be considered a service disconnect.
The MSP is in the garage, next to a door that appears to connect to the interior of the home.
Note that the door in this image does not match the exterior door that appears by the meter.
This means the MSP must be over 10' away from the meter.
A load side connection could be considered to avoid needing an indoor flush mount OCPD load center. We will need to see the inside of this panel before we can make a judgement on this.
This is a Pushmatic panel, marked by the push button style breakers. Though there are listed replacement breakers for this type of panel that we can use for interconnection when needed, this is restricted in some markets and a supply side tap would be preferred.
This project is in Oregon, which is a market where breaker type connections are not allowed on Pushmatic panels.
We need to verify that a supply side tap is possible.
Looks like we have over 5" of service conductor which is the minimum length needed for typical piercing connectors.
A supply side tap was chosen due to restrictions on load side connections on this type of panel in this market. Due to the MSP being indoor and away from the meter, an indoor breaker type OCPD is needed.
Here's the basic run down:
Best form of interconnection when available.
Can backfeed up to the bus rating of the panel for supply side connections.
Only available when:
AHJ uses 2017 NEC or earlier and there are less than 6 service disconnects on the supply bus.
AHJ allows for grandfathering service equipment with 6 handles on the 2020 NEC
Load center has a designated solar ready position regardless of NEC Code year.
Not available when AHJ enforces the single main disconnect rule per 2020 NEC
As summarized above, the 2020 edition NEC prevents the use of supply side breaker connections in most situations. Let's dive into the changes to service requirements that were instated with the 2020 edition of the NEC:
230.85 Emergency Disconnects:
For one- and two-family dwelling units, all service conductors shall terminate in disconnecting means having a short-circuit current rating equal to or greater than the available fault current, installed in a readily accessible outdoor location. If more than one disconnect is provided, they shall be grouped.
2017 NEC and prior: there was previously no requirement for there to be an accessible emergency disconnecting means outdoors. In many older markets such as Virginia, Oregon, South Carolina, etc., you will often see "stand alone" meters, meaning that the main disconnect/MSP is indoors somewhere which was allowed in older versions of the code and may be grandfathered in.
The principle difference is that the 2020 NEC requires an outdoor accessible emergecny service disconnect.
230.71(B) Maximum Number of Disconnects:
Two to Six Service Disconnecting Means. Two to six service disconnects shall be permitted for each service permitted by 230.2 or for each set of service-entrance conductors permitted by 230.40, Exception No. 1, 3, 4, or 5. The two to six service disconnecting means shall be permitted to consist of a combination of any of the following:
(1) Separate enclosures with a main service disconnecting means in each enclosure
(2) Panelboards with a main service disconnecting means in each panelboard enclosure
(3) Switchboard(s) where there is only one service disconnect in each separate vertical section where there are barriers separating each vertical section
(4) Service disconnects in switchgear or metering centers where each disconnect is located in a separate compartment
2017 NEC and prior: a residence was still only allowed up to 6 service disconnects, however, it used to be allowed to have all 6 service disconnects in a single enclosure.
The principle difference is that the 2020 NEC requires each service disconnect to be in a separate enclosure with only one main service disconnect per enclosure.
230.67 Surge Protection:
(A) Surge-Protective Device. All services supplying dwelling units shall be provided with a surge-protective device (SPD).
(B) Location. The SPD shall be an integral part of the service equipment or shall be located immediately adjacent thereto.
Exception: The SPD shall not be required to be located in the service equipment as required in (B) if located at each next level distribution equipment downstream toward the load.
(C) Type. The SPD shall be a Type 1 or Type 2 SPD.
(D) Replacement. Where service equipment is replaced, all of the requirements of this section shall apply.
2017 NEC and prior: This is another service requirement that did not exist prior to the 2020 NEC.
The principle difference is that the 2020 NEC requires each service to be equipped with an SPD.
Solar ready panels will always allow supply side breakers regardless of the code cycle year being enforced.
But how do we know if an AHJ using 2020 NEC will allow us to complete a supply side breaker on a split bus on main lugs panel?
Check the 2020 NEC Labeling section of the design tool cover page.
Many jurisdictions, even those that are technically using the most up to date edition of the NEC will allow for grandfathering older services, so be sure to check this labeling in the BASELINE DT to double check if it is allowed or not.
Example of an AHJ on 2020 NEC not enforcing the “single main disconnect per enclosure” requirement. Main lug/split bus MSP are allowed here and we can land a supply side breaker.
Example of an AHJ on 2020 NEC enforcing the “single main disconnect per enclosure” requirement. Main Lug/ Split bus MSP are not allowed here, therefore, no supply side breaker.
So, what exactly is a Solar Ready Panel?
Some Meter/Main combos have a solar ready position at the top of the panel. Usually marked by:
Bus diagram showing a dedicated slot for secondary customer generation.
A slot in the MSP deadfront labeled as a second service disconnect spot
A spot at the top of the bus that is separate from the rest of the MSP busing.
A solar ready position is a designated space made for secondary power sources and can always be used regardless of code year. This will make your job a lot easier if you see this.
Make sure to check the rating for the solar ready position. In the example on the right, the solar ready position is rated for 100A which would be plenty to accommodate the backfeed produced by most residential systems, however, you still need to be mindful:
Some solar ready positions are only rated for 50A.
A large system may exceed 50A of backfeed, so it important to factor this in when choosing this type of interconnection.
When the panel sticker does not have a legible rating on it we will need to assume it is only rated for 50A.
In this configuration, double check how your bus is being fed.
Notice a 2P 125A breaker installed in this panel. Is this the main breaker?
No. If you turned this breaker to the off position, the bus is still energized by the main lugs coming from the meter.
It’s only the main breaker if it is attached to the main lugs.
In this configuration, both the 125A breaker and the 20A breaker are considered service disconnects, therefore, the 20A PV breaker beside it is a supply side connection.
Similar to the configuration above, look for where the main lugs are located. in this case it is apparent that there is no main breaker. The next thing to check is the labeling of the panel to confirm the bus layout for the supply side bus and the sub bus.
PV breaker can be landed on the top supply side bus.
No more than 6 handles on a supply side bus.
Here we have an outdoor meter/main with a dedicated solar ready position at the top.
This is marked by the bus diagram.
You can also see dedicated service conductors connected to terminals for this specific spot at the top.
Note that this spot is only rated for about 50A.
Based on the system size info bellow, we have a 19 panel system. This means the total backfeed is 30A which means that this solar ready position is more than capable of handling our PV.
In addition, it appears that there are feed through lugs at the bottom of this panel, meaning that we would need to ensure that the feeders connected to them are properly protected if we wanted to consider a load side connection.
completing a supply side connection would mean that we are not even connected to the bus supplying the feedthrough conductors, so we would not need to worry about protecting those feeders in anyway.
A supply side breaker was the clear winner all around.
In this example, we have a split bus panel where the top 12 spots are considered service disconnects. The breaker on the lower left of the upper bus is supplying the lower bus.
Notice that is appears that this bus would be over the 6 handle rule, however, we have breakers on this bus that are not in use.
We can disregard these breakers that are not in use which would make the total 4 handles on this bus.
We were able to place our PV breaker on the supply side bus for a supply side breaker connection by removing some of the unused breakers.
note that the total number of handles is now 5 including PV.
We will be focusing on the electrical portion of this project and combining the pieces that we've gone over so far throughout training.
The first thing we notice is that the MSP does not appear to be near/adjacent to the meter. It is important to keep a mental map of where the meter, MSP and any sub panels are in relation to each other as it will make interconnection decisions a lot easier.
The next thing to take note of is where we will be placing the PV wall equipment beside the meter. It appears that there is plenty of space to the right of this meter to mount any equipment including the combiner, and any AC disconnect or PV meter that may be required by the utility.
We can also likely use this photo as a reference point to figure out the position of the MSP. Use this window as a landmark.
In this zoomed out panoramic, the MSP is located to the very right.
You can see the window we were using as a landmark in the red box. This means the MSP is on the opposite side of the garage from the meter on an interior wall of the home.
This can be an important factor to consider for a couple of reasons:
If there is a sub panel on the exterior of the home somewhere, it may be more efficient to interconnect on the sub panel.
If the only option is a supply side tap in the MSP, we need to make sure we can mount an indoor breaker type OCPD by the MSP.
We will keep a mental note of this, but it is important to investigate every photo and every note from the survey.
Now we need to start screening and qualifying the equipment.
For this MSP, we need to create a homeowner obligation to remove this shelving because it violates the required working space clearance for the panel.
We'll add this to our data collection.
This appears to be a split bus panel as there is not single main breaker at the top.
This is further verified by the breaker labeled as "120 V Main"
This would be the breaker supplying the lower bus in this load center.
This also confirms that this is the only panel in the home.
If there were additional panels, they would be feeding from this panel and labeled here.
It is also of note that there is a breaker that is not in use labeled as "spare" opposite the "120 V Main."
We will need to confirm that there are no loads connected to this but we will be at liberty to use this spot for PV if it is not already being used.
When you see a split bus panel, you should make sure that 6 handles are allowed in the area you are working in. This can be confirmed in the AHJ/Utility requirements in the BASELINE DT by plugging in the correct AHJ/Utility and checking for this.
If you are familiar with the general rules of the market, such as this project which is in Oregon, you may already have an idea of if it is allowed or not.
All of Oregon is on a custom statewide code that will allow for 6 handles.
Now we need to confirm the bus layout and that we're not over 6 handles.
On a first glance, it appears that the top six breakers are on the upper supply side bus with everything bellow these breakers being on a separate sub load bus.
We can also confirm that there are no conductors connected to the "spare," so supply side breaker should be on our radar as the preferred interconnection for the time being.
We also need to confirm that the tandem breakers at the bottom of the bus are allowed.
The labeling confirms both the bus configuration and that tandems are allowed in the bottom most 2 positions only.
While we're looking at the label, we can also verify the bus rating. This will be added to our data collection.
We also need to look for any other code violations or damage on this panel.
The only other issue of note here is that this is an I-T-E panel, so only I-T-E original breakers or Siemens brand breakers should be installed in this panel.
The two breakers in the red boxes are Bryant and Eaton type breakers that will need to be replaced.
We will add this to our data collection.
The 200A bus should be plenty to accomedate the system backfeed, but we still need to do our due diligence.
The financials of this project specify an 18 panel system. This will produce 30A of backfeed when the backfeed calculation is completed. We should be in the clear to complete a supply side breaker as planned.
Here's what our electrical data collection should look like on paper:
Everything we need to complete the electrical part of the design is here
Having this written out in short hand ensures that none of this will be missed on the backend of the design process.
This includes not just the interconnection type, bus rating and make/model callout but also homeowner obligations and replacement breakers for the noncompatible breakers that are currently installed.
TAKE A MOMENT TO TEST YOUR KNOWLEDGE
If you're not already signed in, you'll have to log in and then navigate to the test manually: