EXTERIOR/INTERIOR - LOAD SIDE BREAKER - EXISTING SUB PANEL MAIN
Design
EXTERIOR/INTERIOR - LOAD SIDE BREAKER - EXISTING SUB PANEL MAIN
Design
WHAT IS LOAD SIDE?
Equipment downstream (below) from the main disconnect breaker
This equipment can be de-energized by switching off the main breaker.
The example to the right shows what your setup might look like for this type of interconnection. Depicted is a meter/main combo. Not shown is the panel labeling indicating spots which will accept tandems. A designer would likely decide to consolidate their PV breaker on a quad with the top breaker farthest away from the main breaker, however, special attention will be required. Notice that there are feeders coming from the bottom lugs of this panel feeding a sub panel. These feeders need to be protected in some way.
This interconnection has the following requirements that need to be met before it can be considered:
Sub Panel feeding from the bottom lugs of the MSP has an existing main breaker.
There are 2 available stabs to accommodate our PV breaker in the MSP.
If you the panel is full but the load center allows tandems you can consider this condition met.
There must be no code violations present in and around the MSP.
If there is a plan in place to resolve code violations, then you can consider this condition met.
There must be sufficient available backfeed for the amount of PV we will be landing in this load center.
In this case, the interior sub panel is already protected by a main breaker rated for 200A.
Below is an example of what this interconnection design will look like in BASELINE DT.
Ratings will vary based on what the set up is.
It will be custom for every site; do not use these exact ratings if you are referring to this page to help choose your interconnection.
Below is an example of what this interconnection design will look like in BASELINE CAD.
Always use the exact verbiage that populates in the "Interconnection Block" on the Utility Requirements of the BASELINE DT.