EXTERIOR/INTERIOR - LOAD SIDE BREAKER - MAIN SERVICE PANEL
Design
EXTERIOR/INTERIOR - LOAD SIDE BREAKER - MAIN SERVICE PANEL
Design
WHAT IS LOAD SIDE?
Equipment downstream (below) from the main disconnect breaker
This equipment can be de-energized by switching off the main breaker.
The example to the right shows what your setup might look like for this type of interconnection. Depicted is an outdoor meter/main combo. The setup for this type of interconnection could also look like an exterior MSP beside the meter but not in a meter/main combo.
This interconnection has the following requirements that need to be met before it can be considered:
MSP can be either interior or exterior.
Remember that exterior connections are always preferred when possible.
There are 2 available stabs to accommodate our PV breaker.
If you the panel is full but the load center will allow you to consolidate the number of spaces you will need on tandems/triplexes/quads you can consider this condition met.
There must be no code violations present in and around the MSP.
If there is a plan in place to resolve code violations, then you can consider this condition met.
There must be sufficient available backfeed for the amount of PV we will be landing in this load center.
Below is an example of what this interconnection design will look like in BASELINE DT.
Ratings will vary based on what the set up is.
It will be custom for every site; do not use these exact ratings if you are referring to this page to help choose your interconnection.
Below is an example of what this interconnection design will look like in BASELINE CAD.
Always use the exact verbiage that populates in the "Interconnection Block" on the Utility Requirements of the BASELINE DT.
The highlighted breaker represents the PV breaker. Notice it says (N).
Always ensure that the bus rating, main breaker rating, and new PV breaker rating pull over from the BASELINE DT after datalinking when completing the Plan Set.