14-15th Feb
the 14th was the first day we started the project, me and chole did the survey for the class and on that same day we started to do the shot list but we were constantly waiting for Callum to update the script so that set us behind a lot but sometimes shots we had already had done changed. me, Chloe and byrun were all working on the shot list whilst deacon was doing market research which should have been completed on the first day so that left in a sticky ;place as we needed him and every time he told us he was doing market research
27-1st Feb-mar
we started on the story board making sure we got all the angles right and that they matched up to the shot list we had ran into a few problems as it was only me and Chloe a lot of the time and we both had to do the shot list and story board and we got the final script which had changed drastically and that meant we had to go back through everything and change it to fit the script.
6-8th mar
me and Chloe went around collage to practice filming some shots we were unsure about like the rack focus (shift in focus) we tried it with 35-50mm lens and it wasn't giving us the effect we wanted and then Caitlin said she has a little lens which was only (insert camera lens here) which was a lot better and it made a really cool effect which is called the bokeh effect it allows you to blur the lights in the back of the shot. i also helped with the start of set design like looing at the story board and figuring out what what where then on the Wednesday we started to paint the walls me Nate and Caitlin stayed after to clean up all the boards.
13-15th mar
this was the first week of filming we worked on the workbench scenes as they took up the most of the episode these were pretty easy to bang out as it was a lot of just her working on the vr then on the Tuesday we went outside to film all of those scenes some we hadn't got round to doing so we had to go out again to shoot those it was a little difficult as where matt wanted to fil it was in front of a shop and we couldn't get anyone in it but we trailed and errored shots and on the Wednesday we filmed some of the bedroom scenes
20-22nd mar
we finished off the bedroom scenes then the editors looked over footage and said a lot needs re filming which put us in a sticky situation as we only had 3 days left of filming but they are going to make it work as we dint have much time and on top of that everyone was feeling ill and not too good and that meant filming isn't going to go as planned we filmed the technician scene and were planning to go out filming again for the shots we missed managed to get those done and then on the Wednesday no one was in as they were all ill which set us back and this was the time we had Niki so we could have got lots done but matt scrapped lots of scene jut to speed up the time and then Paris received some news which meant filming got put to a stop she returned at lunch but matt didn't want her filming so he called it off for the day and luckily we could film on Monday.